Delegated Report - Code - Planning OPW26 0069 (As Published)

of 17
               2.     APPLICATION BACKGROUND
               The information provided as part of the application was sufficient for Council to assess. A Request
               for Information was not issued.
               3.     SITE DETAILS
               3.1. Site History
               The application is required to comply with the higher order approval MCU25/0118.
               The application is over land that has not yet been titled but has been approved by Council
               (RAL25/0005). The works required to facilitate the titling of this lot are ongoing.
               3.2. Site Description
               The subject site is under going construction as part of RAL25/0005.
               3.3. Surrounding Land Uses
               The subject site adjoins a future drainage lot (Bioretention Basin), vacant land and a cemetery.
               4.     ASSESSMENT
               4.1. Instruments for Statutory Assessment
               Under the Planning Act 2016 the application must be assessed against each of the following
               statutory planning instruments to the extent they are relevant to the development:
               •      State Planning Policy;
               •      South East Queensland Regional Plan;
               •      Planning Regulation 2017; and
               •      Noosa Plan 2020 (20 March 2026).
               4.2. Noosa Plan 2020
               The following codes from the Noosa Plan 2020 are applicable to this development:
               •      Works Codes
               The application has been found to generally comply with all applicable statutory instruments. The
               pertinent issues arising out of the assessment are discussed below:
               Access
               The proposal seeks to take access from a new, Council-owned Road which is currently under
               construction. The access has been designed to generally comply with Council’s standard drawing
               RS-051.
               Stormwater
               The proposal seeks to capture all runoff via a new underground pipe drainage network before being
               discharged to two future stormwater pits (to be provided as part of the creation of the Lot) to serve
               as the Lawful Points of Discharge.
               All impervious areas of the development are to be provided with an on-site detention tank that has
               been sized to ensure that post-development flows will not exceed pre-development flows for all
               events up to, and including, the 1% AEP storm event. A climate change allowance was always
               included pursuant to Council’s Planning Scheme Policy 6 Engineering Design Standards.
               Stormwater quality treatment is not provided as part of these works, as the development site
               discharges into a Council-owned bioretention basin that has been sized to accept flows from the
               developed subject site.
               Erosion and Sediment Control
               Engineering recommends a full suite of erosion and sediment control conditions, including, but not
               limited to:


                                                                                                      Page 3 of 17

Document Set ID: 25035493
Version: 2, Version Date: 07/08/2026

Log in to download the original (Delegated Report - Code - Planning OPW26 0069 (As Published).pdf)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.