Delegated Report - Code - Planning OPW26 0069 (As Published)

of 17
               CURRENCY PERIOD
               2.     The Currency Period for this development approval lapses if the development has not
                      substantially started by 5 August 2028, unless an application to extend the currency period
                      is approved by Council.
               SITE SPECIFIC CONDITIONS
                      Erosion and Sediment Control Plans
               3.     Submit a site-specific Erosion and Sediment Control Plan in accordance with the
                      International Erosion Control Association’s (IECA) Best Practice Erosion and Sediment
                      Control and prepared by a suitably qualified person (RPEQ and/or CPESC). The Plan must
                      be submitted prior to the commencement of works.
               4.     Prior to the commencement of bulk earthworks:
                      a.      a hold-point inspection is required with a Council delegate to review that the erosion
                              and sediment controls on-site generally reflect the Erosion and Sediment Control Plan.
                      b.      certification from a suitably qualified person (RPEQ and/or CPESC) must be submitted
                              to Council certifying that the erosion and sediment controls on site have been installed
                              in accordance with the Plan and IECA’s Best Practice Erosion and Sediment Control
                      Bonds
               5.     A performance bond of $5,000 is to be submitted to Council prior to the pre-start meeting.
                      The pre-start meeting will only be held once Council's Construction Engineering Officer has
                      confirmation that the bond monies have been received by Council.
                      The bond will be refunded less any costs incurred by Council, including but not be limited to,
                      any bond administration fees, ensuring compliance with the conditions of this approval, or
                      any additional inspections incurred for substandard work or work undertaken not in
                      accordance with this approval.
               6.     Bonds must:
                      a.      meet the requirements of Council’s Planning Scheme Policy 4 Performance Bonds and
                              Planning Scheme Policy 6 Engineering Design Standards;
                      b.      be calculated based on an agreed schedule of works (for Maintenance Bonds only);
                      c.      be lodged to Council with the relevant bond administration fee(s); and
                      d.      be requested for release by writing to Council when relevant approval requirements
                              have been met.
                      (*) Refer to Advisory Note
               PRIOR TO COMMENCEMENT OF WORKS
                      Engineering
               7.     Council must be contacted at least 5 working days prior to any works commencing to
                      organise a prestart. The contact number to arrange a pre-start meeting is 5329 6500. The
                      pre-start meeting must include the relevant parties for the following aspects of the works:
                      a.      civil engineering works;
                      b.      landscape works;
                      c.      erosion and sediment control works; and
                      d.      other relevant parties.
                      A proxy may be nominated for any party unable to attend the meeting. Council must be
                      notified of any proxies prior to the pre-start meeting.




                                                                                                        Page 9 of 17

Document Set ID: 25035493
Version: 2, Version Date: 07/08/2026

Log in to download the original (Delegated Report - Code - Planning OPW26 0069 (As Published).pdf)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.