                                                                                           Callaghan & Toth

Actions                  Owner to maintain rainwater / stormwater dam systems as follows and conduct
                         six monthly inspections:
                              •   Check gutters for leaf litter
                              •   Check stainless steel mesh guards are in place
                              •   Check first flush system is functioning
                              •   Check overflow is not causing any scour
                              •   Check float switch is functioning
                         Owner to also conduct periodic assessments (approx. 5 to 10 years) to
                         determine whether sediments deposits require removal from within the tank.

Monitoring               Owner to monitor rainwater tank systems as detailed above.



Reporting                Records are to be logged and kept for verification of compliance on a need
                         basis.

Incidents                     •   Rainwater tanks has been removed or disconnected
                              •   Rainwater tank system is faulty e.g. roof, guttering, first flush system or
                                  tank is damaged.
                              •   Overflow has been disconnected from absorption trench
                              •   Overflow is causing scour.
                              •   Rainwater tank capacity is insufficient for demand.

Corrective Action        Owner will be required to :
                              •   Reinstall or connect rainwater tank
                              • Main    tain rainwater tank system
                              •   Reconnect overflow to absorption pit (if exist on lot)
                              •   Stabilise overflow discharge area or move to more appropriate
                                  location.
                         Owner to investigate providing extra roof area for rainwater collection to allow
                         installation of extra rainwater tanks.
                         Owner to investigate treating excess stormwater from access roads and
                         carparks to potable water quality to meet demands.



                                     VEGETATED BUFFERS
ISSUES                   PROCEDURES

                                                Design Phase

Objective                Ensure that vegetated buffers are maintained with vegetated cover and
                         overland flowpaths are maintained as sheet flow.




                                                                                                       G
1209 Animal Husbandry – Top Forestry Rd, Ridgewood                                    SWQMP_REV_3
SEPTEMBER 2013
Log in to download the original file

1209 SWQMP Report_3 2013.pdf · 4.9 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.