Construction Management Plan - Unit 15 The Hastings - 100217 · 51983.3225.06

Attached to the e-mail Construction Management Plan & Traffic Management Plan 51983.3225.06.

of 13

Check the original when the exact wording matters.

Plans and drawings: the text below has words only, no drawings.

Log in to see the plans as drawn
      1 Introduction

      1.1 Purpose

      This Construction Management Plan has been documented to describe how the Project Management team shall
      implement and conduct its allocated site management responsibilities during the Construction phase of the ‘Unit 15
      The Hastings, 30 Hastings St” Project (the Project). A fundamental aim of this Plan is to ensure all construction is
      properly facilitated, integrated and coordinated to deliver certainty to the objectives of the Project.



      1.2 Scope of this Plan

      This Plan provides a holistic approach that:

             advises how the project management team will comply with the requirements of the contract relating to
              construction;
             defines the project objectives and targets of particular relevance to the construction phase;
             describes constraints specific to the construction phase and the project in general;
             describes the process for the identification and control of risks specific to the construction phase; and
             details the proposed strategy for the construction phase, with particular regard to establishment resourcing,
              site organisation and construction controls.


      1.3 Proposed Works

      The proposed works require the construction of:

             Ground Floor including garage and lift – Refer Drawing DA.04
             First Floor, bedrooms and bathroom – Refer Drawing DA.05
             Second Floor, living, dining and kitchen - Refer Drawing DA.06
             Roof Terrace, plunge pool and outside living areas – Refer Drawing DA.07


      This type of construction will have several distinct phases that will require different material handling strategies to
      optimise the construction works and minimise impact to surrounding streets, other stakeholders and neighbours. Our
      material handling strategies and Construction planning will be consulted with stakeholders and authorities before
      implementation.



      1.4 Site Location

      The proposed development site (refer Figure 1 and 2) is bounded by Noosa Parade and Hastings Street. The site is
      known as “The Hastings”.




CONSTRUCTION MANAGEMENT PLAN – FEB 2017                                                              RG STRATEGIC

Used in these records

About this file

File size
3.9 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Construction Management Plan - Unit 15 The Hastings - 100217.pdf · 3.9 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.