Construction Management Plan - Unit 15 The Hastings - 100217 · 51983.3225.06

Attached to the e-mail Construction Management Plan & Traffic Management Plan 51983.3225.06.

of 13

Check the original when the exact wording matters.

Plans and drawings: the text below has words only, no drawings.

Log in to see the plans as drawn
      2 Construction Management

      2.1 Approach

      The major external constraints on the project are:

             Maintaining smooth traffic and pedestrians flow with minimal disruptions to Bay Village, Sofitel and The
              Hastings access;
             Undertaking works with minimal impact on neighbours, in particular, Bella Casa apartments; and
             Ensuring Noosa Parade and Noosa Parade Service Rd are unaffected.


      Upon commencement, our project team’s immediate tasks will be to:

             Locate a project office, site accommodation and facilities;
             Undertake a survey of the site and complete a dilapidation report of surrounding properties and assets;
             Confirm the locations of existing services and obtain all necessary permits and licences and approvals; and
             Arrange for the installation of temporary services – power, water and sewer to service the site works and the
              amenities.


      2.2 Approvals

      A Development Approval has been issued for the proposed development - 51983.3225.06.

      It is proposed that staged Building Approvals (BA) will be obtained from a qualified Private Certifier (PC). It is
      proposed that the BA will be approved in the following sequence:

             Demolition and site prep works.
             Structural works for ground floor.
             Structural works for first, second floor and roof top.
             Services and Internal Fit Out


      We do envisage that Staged occupation will be required.


      The staging of the BA’s will allow works to commence, whilst affording time for those works requiring intense design
      time such as structural and finishes works. The net effect is an overall reduction in total development construction
      time.



      2.3 Site Security

      The site will be secured using appropriate fences and/or hoardings, with access gates manned with qualified security
      guards/traffic control officers. The site will be secured out of hours and patrolled by qualified security guards. All
      visitors to the site will be required to report to the site office, and will be appropriately inducted and registered in a
      visitor’s log book.




CONSTRUCTION MANAGEMENT PLAN – FEB 2017                                                                 RG STRATEGIC

Used in these records

About this file

File size
3.9 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Construction Management Plan - Unit 15 The Hastings - 100217.pdf · 3.9 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.