      2.4 Public / Worker Safety

      All site staff and subcontractors will be required to complete a site specific induction before commencing work on site.
      The induction will cover aspects relating to safety and amenity; including access, emergency evacuation procedures,
      location of first aid facilities, location of amenities, site hours, material handling, noise and dust policies and
      environmental management.

      Prior to commencing works on site, all subcontractors will be required to submit a project specific Safety Management
      Plan. This plan will be reviewed by Chris Smith Construction (CSC) for compliance with the overall Project Safety Plan.

      A Safety Committee will be established during the early stages of the project. The committee will have representatives
      from subcontractors and CSC. It will conduct regular inspections of the project, and will be actively involved in
      reviewing Safety Management Plans and making recommendations with regard to health and safety issues.

      The Contractor is to maintain access to all adjacent properties during the construction of these works.



      2.5 Traffic Management Plan

      To be submitted to Council for approval by the selected Contractor (Refer Appendix – Traffic Management Plan Ref
      No:139614).

      All temporary traffic control to be in accordance with the MUTCD.



      2.6 Communications Protocol / Complaints Procedure

      The appointed Contractor shall undertake a letter box drop to neighbouring properties providing contact details for
      the site supervisor.



      2.7 Existing Infrastructure

      Existing infrastructure will be protected during construction. The selected Contractor shall clean off any debris
      deposited on the road. Dial Before You Dig enquiries will be undertaken prior to all excavation works.



      2.8 Fencing

      The site Security Fencing will consist of temporary secure fencing – 2m high. Gates will be used on all access points
      onto the site.




CONSTRUCTION MANAGEMENT PLAN – FEB 2017                                                               RG STRATEGIC

Used in these records

About this file

File size
3.9 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Construction Management Plan - Unit 15 The Hastings - 100217.pdf · 3.9 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.