4.4 Stormwater and Sediment Control
A stormwater and sediment control plan will be developed and will be implemented prior to works commencing.
This will ensure that stormwater from the development does not enter adjoining properties, and that all water that
enters the council stormwater system does not contain silt or other contaminants.
The following are possible solutions during each phase of construction. These options will be developed further and
consolidated into the overall management plan.
Demolition / Excavation – At the commencement of these works, screens and bunding at the perimeter of the site
where stormwater may run off will be installed. Bunding will also be implemented around stormwater drains.
Diligent housekeeping will be implemented to minimise risk of dust/debris being washed into pits.
Construction – The building slab drainage will be progressively installed and connected to council drains. Drainage
pits will be bunded or have filter cloth applied to ensure debris and silt does not enter the council’s drains.
CONSTRUCTION MANAGEMENT PLAN – FEB 2017 RG STRATEGIC
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Construction Management Plan - Unit 15 The Hastings - 100217.pdfRelated documentApplication case desk ↗
About this file
- File size
- 3.9 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.