4 Environmental
4.1 General
The objective of this section is to identify the proposed methods that will be employed to minimise the impact of
noise, vibration and air quality in the vicinity of the development.
4.2 Noise and Vibration Management
The normal hours of work will typically be 7.00am to 5.30pm, Monday to Saturday excluding public holidays. Noise
management will generally be in accordance with the QLD DEHP environmental noise management criteria. All plant
will be regularly maintained and log books kept ensuring that there are no excess noise emissions. Where it is practical,
electric machinery will be used in lieu of mechanical devices.
All subcontractors will be responsible for managing noise and vibration in accordance with their project specific
Management Plans.
It is proposed to undertake some after hour’s works for specific tasks to minimise impacts to pedestrians, vehicular
traffic or in the interest of safety. The works that are proposed to be undertaken outside of normal working hours
include the following:
Removal tree’s;
Fencing works;
Crane erection and dismantling; and
Footpath works.
All after hour’s works will be subject to the Communication Management Plan. Consultation with the Noosa Shire
Council will occur at all times prior to any works being scheduled. All businesses and surrounding residents will be
given notification via email, letter box drop and personal contact of all the proposed after hours works prior to the
works commencing which will include details of the works and the time to undertake each activity.
4.3 Air Quality / Dust Management
Dust control measures will be implemented as required, and will be in accordance with QLD Workplace health and
safety regulations and Environmental Protection Act.
Dust Management will be most critical during the demolition phase of the project, with the subcontractors for these
trades specifically dealing with dust management within their project specific management plans.
Measures that may be employed include:
Demolition – All trucks removing materials from site will be loaded whilst inside the site perimeter, with loads
covered before exiting.
Excavation – water down working surfaces as required. Minimise stock piling of material. Maintaining
stabilised access roads and driveway.
Construction – Maintain a high level of housekeeping to minimise likelihood of windblown dust.
CONSTRUCTION MANAGEMENT PLAN – FEB 2017 RG STRATEGIC
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Construction Management Plan - Unit 15 The Hastings - 100217.pdfRelated documentApplication case desk ↗
About this file
- File size
- 3.9 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.