Appendix B Code Compliance Statements · MCU22/0038

of 72

Text shows just the words. Original shows the document exactly as it was published.

Check the original when the exact wording matters.

Noosa Business Centre – Lot 22 Medihub                                                                                                Noosa Plan 2006 dated June 2018

                                                                                                   Compliance
 Specific Outcomes                                         Probable Solutions                                   Response
                                                                                                   ü/û/NA
  a)   0.8:1 for site areas up to and including
       2,000m2; plus
  b)   0.3:1 for the balance portion of the site area in
       excess of 2000m2.

 O16 For the Shire Business Centre Zone, the                                                             ü      Compliant – Specific Outcome
 maximum plot ratio for development within the
                                                                                                                The applicable maximum plot ratio for the proposed
 following precincts is —
                                                                                                                development is 0.8 as the development site is located
  a) Precincts B1 and B2 combined- 0.5:1;
  b) Precinct B3- 0.8;                                                                                          within the Precinct B3 of the Shire Business Centre Zone.
  c) Precinct E1- 0.6;
  d) Precinct E2- 0.6;                                                                                          The proposed development provides a plot ratio of 0.56:1
  e) Precinct E3- 0.6, except for Industrial business                                                           which is well below the prescribed maximum plot ratio.
       uses;
  f) Precinct E4- 0.6; except for Industrial business
       uses;
  g) Precinct E5- 0.6, except for Industrial business
       uses;
  h) Precinct E6- 0.6;
  i) Precinct E7- 0.6;
 Precinct RES- 0.6; and Precinct REC/MU- 0.1.
 Flooding and drainage                                     S17.1                                         NA     Not Applicable
                                                           For new buildings or structures or
 O17                                                                                                            The development site is not affected by flood.
                                                           additions of more than 50m2 gross
 Buildings and other works are designed andsited to—
                                                           floor areato an existing building or
  a)     provide flood free access to premises andflood
                                                           structure, floor levels for habitable
         free habitable areas;
                                                           rooms are not less than the specified
  b)     allow only minor, short term and infrequent
                                                           minimum floor levels;
         flooding of non-habitable areas;
                                                           AND
  c)     ensure carparking areas can be adequately
                                                           S17.2
         drained;
                                                           Where Council infrastructure
  d)     ensure drainage does not adversely impact
                                                           isavailable—
         upon other premises; and
                                                             a)     any drainage (including
  e)     ensure filling or excavation does not
                                                                    buildings andyards) flows to
         adversely impact upon other premises by—
                                                                    that infrastructure; and
          i.     causing ponding on the site or nearby
                                                             b)     the infrastructure has the
                 land;

                                                                                                                                                                 Page | 8

Used in these records

About this file

File size
332 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Appendix B Code Compliance Statements.pdf · 332 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.