THE NOOSA COMMUNITY
No. Project Responsibility Update SSE LUEs
1 Implementation of Social Strategy: Director Community Services Purchase of Johns Landing finalised 22 November 2017. Demolition of Completed Qo
- Purchase of Johns Landing and transition of long term buildings and final clean up finalised in March.
residents to alternative accommodation
- Finalise development of Arts and Cultural Heritage Plan and Director Community Services Draft plan endorsed by Council in May 2018 for the purpose of On track @
commence implementation community consultation. Community engagement regarding draft plan
scheduled for July/August.
- Finalise development of Sport and Recreation Plan and Director Community Services The final plan endorsed by Council in the October 2017 round of Completed o
commence implementation meetings. Action Plan developed.
2 Commence community consultation for an iconic playground at Infrastructure Planning, Design & Delivery A draft project management plan has been developed which includes On track @
Cooroy Manager stakeholder analysis, communications requirements, reporting and metric
collections.
3 Implementation of Library Strategic Plan Libraries and Galleries Manager Noosaville Library refurbishment works commenced in April 2018 and On track 6
Radio Frequency Identification Technology implementation project
underway.
4 Partner with the Cooroy Memorial Hall Committee for building Infrastructure Planning, Design & Delivery Cooroy Memorial Hall re-opened on 21 April 2018. Completed 6
restoration and refurbishment Manager
5 Develop a Regional Art Gallery Strategy Libraries and Galleries Manager Development of the Regional Gallery strategy has commenced following Behind Schedule @
the appointment of the new Gallery Director and the finalisation of the
Draft Cultural Plan.
THE NOOSA ECONOMY
No. Project Responsibility Update Ry cay
1 Commence renewal of Park Road boardwalk Infrastructure Planning, Design & Delivery Construction has commenced. On track @
Manager
2 Finalise construction of Rufous Street Digital Hub project (Stage Economic Development Manager Construction of the Digital Hub building and restoration of the Completed @
1) and adoption of hub operating model surrounding parkland completed. New Director of Digital Hub appointed.
Tender for tenanting of Digital Hub completed. Tenants commence
moving in July 2018.
3 Continued implementation of Local Economic Plan_ incl. Economic Development Manager Continued to deliver on Local Economic Plan Priority actions, highlights Completed 6
providing support to existing industry representative groups and include:
evaluation of peak body models - The ongoing rollout of the Economic Grants Program and guidance
being provided to a range of industry representative groups on potential
initiatives; and
- Strong industry engagement in relation to the development of the New
Planning Scheme. Strong and productive elationships continuing with
key stakeholders and industry representative groups.
Page 157 of 165See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.