SERVICES & ORGANISATION COMMITTEE MEETING AGENDA 7 AUGUST 2018
Page 26 of 165
SERVICES & ORGANISATION COMMITTEE MEETING AGENDA 7 AUGUST 2018
The IBI Report App. 3 has been annotated with the Programme Activity number which
corresponds to the relevant maintenance item.
6. CONCLUSIONS
The Association is proposing to undertake the following work on the hall: -
e Maintenance work estimated to cost $148,000
e Upgrade work to kitchen, toilets and entries estimated to cost $216,000
e Total estimated project cost $384,000, including $20,000 Contingencies/
Overheads with a project completion time of 6 months
e Approximate value of in-kind support estimated to be 40% of project cost
($154,00), hence Council support/Grants required to the value of
approximately $230,000
13
Page 26 of 165See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.