Skip to the record
For the highest quality transcripts.

Council archive · source document

Approved Decision Notice - RAL25/0019 (As Published)

of 8

Text shows just the words. Original shows the document exactly as it was published.

Check the original when the exact wording matters.

                                                                                         Officer:             Nadine Gorton
                                                                                         Direct Telephone:    07 5329 6245
                                                                                         Our Reference:       RAL25/0019
                                                                                         Your Reference:      n/a

               19 January 2026


               Stockwell Development Group Pty Ltd
               PO Box 3144
               SOUTH BRISBANE QLD 4101
               [email protected]



               Dear Sir/Madam,
                                                         Decision Notice
                                                         Planning Act 2016

               I refer to your application and advise that on 16 January 2026, Council decided to approve the
               application, subject to conditions.
               Details of the decision are as follows:
               1.      APPLICATION DETAILS

                   Application No:              RAL25/0019

                   Street address:              63, 65, 67 and 69 Hofmann Dr, Noosaville Qld 4566

                   Real property description:   Lots 3, 4, 5 and 6 SP 322201

                   Planning Scheme:             Noosa Plan 2020 (26 September 2025)

               2.      DECISION DETAILS

               Council decided to issue the following type of approval:
               •     Development Permit for a Reconfiguring a Lot - Boundary Realignment
               3.      CURRENCY PERIOD OF APPROVAL

               The currency period for this development approval is stated in the conditions below.
               4.      ASSESSMENT MANAGER CONDITIONS

               PLANNING
               When Conditions Must Be Complied With
               1.      Unless otherwise stated, all works required by the conditions of this Decision Notice must be
                       completed prior to submission of the subdivision plan to Council for compliance assessment.
               Currency Period
               2.      This development approval lapses if the requirements of the conditions have not been
                       completed and an application for plan seal is not lodged with Council by 15 January 2030,
                       unless an application to extend the currency period is approved by Council.

               ABN 97.969.214.121                                                               PO Box 141
               noosa.qld.gov.au                                                          Tewantin QLD 4565
               [email protected]                                                          07 5329 6500
                                                                                                             Page 1 of 8
Document Set ID: 24440260
Version: 4, Version Date: 19/01/2026
Full text of the other 7 pages

Page 2

               Approved Plans
               3.     Development authorised by this approval must be undertaken generally in accordance with
                      the Approved Plans listed in the table/s below.

                        Plan No.               Rev.    Plan/Document Name                               Date

                        SP357720                       Plan of Lots 3 -6                                10.09.2025

               4.     All lot numbering on the subdivision plan to be submitted to Council for compliance
                      assessment must remain as shown on the Approved Plans.
               Boundary Encroachments
               5.     Certification must be submitted to Council from a Registered Cadastral Surveyor (Qld) which
                      certifies that:
                      a.    all constructed access and roadworks (including associated fill batters and retaining
                            walls) are fully contained within a dedicated reserve or registered easement
                      b.    all utility services and connections (eg. electricity, telecommunications, water, sewerage)
                            are wholly located within the lot they serve or alternatively included within an easement
                      c.    all existing effluent disposal areas are wholly located within the lot they serve and comply
                            with the boundary setback requirements of the Plumbing and Drainage Act 2002 and
                            associated codes and requirements
                      d.    all dams (including ponded water, dam walls and associated spillway structures) are
                            wholly located within the boundaries of a single lot
                      e.    all retaining walls and structures are fully contained within the lot they retain
                      f.    any fill, including fill batters, are wholly contained within the subject site and not on
                            adjacent properties
               Water & Sewer Connections
               6.     An underground connection to reticulated water and sewerage must be provided to each lot
                      in accordance with the standards and requirements of Northern SEQ Distributor–Retailer
                      Authority (Unitywater).
                      A Certificate of Completion from the Northern SEQ Distributor–Retailer Authority (Unitywater)
                      must be submitted to Council that certifies an underground connection to reticulated water
                      and sewerage has been provided to each lot.
               Services
               7.     Underground reticulated electricity and telecommunication services must be provided to
                      each lot in accordance with an approval for Operational Works and the standards and
                      requirements of the relevant service provider.
               8.     Unless otherwise stipulated by telecommunications legislation at the time of construction, the
                      development must be provided with all necessary conduits, pits and pipes to accommodate
                      the future connection of optic fibre technology telecommunications.
               9.     Certification must be submitted to Council from all relevant service providers (Energex, NBN)
                      which certifies that the development has met the requirements of this Decision Notice and
                      all applicable legislation at the time of construction.
               5.     REFERENCE DOCUMENTS

               Not applicable.




                                                                                                            Page 2 of 8
Document Set ID: 24440260
Version: 4, Version Date: 19/01/2026

Page 3

               6.     REFERRAL AGENCIES

                Advice Column2: Energex                Schedule 10, Part 9, Division 2,       The agency provided
                       Limited Town Planning           Table 1, Item 1                        its response on 24
                       GPO Box 1461                    (10.9.2.1.1) – Reconfiguring a lot     December 2025
                                                       subject to an easement                 (Reference: ECM
                       BRISBANE QLD 4001
                                                                                              36637435-36637214).
                                                       for the benefit of a distribution
                                                                                              A copy of the response
                                                       entity under the Electricity Act for
                                                                                              is attached
                                                       a supply network; or part of the lot
                                                       is within 100m of a substation site

               7.     ADVISORY NOTES

               The following notes are included for guidance and information purposes only and do not form part
               of the assessment manager conditions:
                      Advertising Devices
               1.     All Advertising Devices must comply with Schedule 10 of Subordinate Local Law No.1
                      (Administration) 2015 including both temporary and permanent signage. All freestanding,
                      pylon or pole signs or signage that is illuminated requires approval from Council prior to being
                      installed. All signage identified in s6 of Schedule 10 of Subordinate Local Law No. 1 is
                      prohibited from being erected in the Shire.
                      Infrastructure Charges
               2.     All developments and/or changes to existing developments may require payment of
                      “Infrastructure Charges” (as applicable) in accordance with Council’s “Charges Resolution”
                      made pursuant to the planning legislation and regulations current at the time of issue. For
                      further       information,     please        refer to https://www.noosa.qld.gov.au/planning-
                      development/development-tools-guidelines/infrastructure-charges
               3.     An applicant for a development application may make an agreement with an assessment
                      manager, referral agency or other person to establish the responsibilities, or secure the
                      performance, of a party to the agreement about a development condition.
               8.     PROPERTY NOTES

               Not applicable.
               9.     VARIATION APPROVAL DETAILS

               Not applicable.
               10.    FURTHER DEVELOPMENT PERMITS REQUIRED

               Not applicable.
               11.    SUBMISSIONS

               Not applicable.
               12.    RIGHTS OF APPEAL

               You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the
               Planning Act 2016 is attached.
               During the appeal period, you as the applicant may suspend your appeal period and make written
               representations to Council about the conditions contained within the development approval. If
               Council agrees or agrees in part with the representations, a negotiated decision notice will be
               issued. Only one negotiated decision notice may be given.




                                                                                                        Page 3 of 8
Document Set ID: 24440260
Version: 4, Version Date: 19/01/2026

Page 4

               13.    OTHER DETAILS

               If you wish to obtain more information about the decision, electronic copies are available online at
               www.noosa.qld.gov.au or at Council Offices.


               Yours faithfully,
               Nadine Gorton
               Coordinator Planning | Development Assessment
               Development & Regulation


               Enc:   Appeal Rights
                      Referral Agency Response
                      Approved Plans/Documents
               cc.    [email protected]




                                                                                                      Page 4 of 8
Document Set ID: 24440260
Version: 4, Version Date: 19/01/2026

Page 5

                                       Referral Agency Response
                                       PLANNING ACT 2016 & PLANNING REGULATION 2017




                                                                                      Page 5 of 8
Document Set ID: 24440260
Version: 4, Version Date: 19/01/2026

Page 6

Document Set ID: 24440260

Version: 4, Version Date: 19/01/2026

Impacted Electrical

Infrastructure

Easements EA, EB, EC ON SP322201 — U/G LV Cables

Energex provides the following response to the application in accordance with Section
56(1) of the Planning Act 2016:

 

 

 

 

Component of Advice Agency direction
Development
ROL O $56(1)(b)(i) — approval subject to stated development

conditions

 

 

In accordance with Section 56(1) should the Assessment Manager decide to approve
the proposed Development Application, as an Advice Agency, Energex requires that
the assessment manager impose the below conditions. These conditions have been
imposed in response to the matters prescribed under Section 55 (2) of the Planning Act

2016.

 

Table 1

 

Plans forming part of this Approval

 

Title

Plan No.

issue

Date

 

Plan of Lots 3-6
Cancelling Lots 3-6
on SP322201
(sheet 1 of 5)

SP357720

 

 

10.09.25

 

 

 

Table 2

 

Condition

Timing

Purpose/Reason

 

1

 

 

Carry out the approved
development generally in
accordance with the
approved plans and
documents outlined within
Table 1 of this approval
and the following:

* The specifications,
facts and
circumstances as
set out in the
development
application
submitted to
Energex: and

* Wherea
discrepancy or
conflict exists
between the
written conditions
of the approval and
the approved
plans, the

 

requirements of the

At all times

 

To ensure the
development is
carried out generally
in accordance with
the plans of
development
submitted within the
application

 

 

Have you seen our fact sheets?

See the ‘considerations when developing around electricity infrastructure’ section of our website

www energex.com auireferralagency

Page 6 of 8

Page 7

Document Set ID: 24440260

 

 

 

 

 

 

 

 

written conditions
prevail
2 | Any alterations to the plans | At all times To ensure the
and document(s) identified development is
within Table 1 of this carried out generally
response are to be in accordance with
resubmitted to Energex for the plans of
comment development
submitted within the
ap ition
General Advice:

* Compliance with the Electrical Safety Act 2002, including any Code of Practice
under the Act and the Electrical safety Regulation 2013 including any safety
exclusion zones defined in the Regulation is mandatory

Should any doubt exist in maintaining the prescribed clearance to the overhead
conductors and electrical infrastructure then the applicant is obliged under the
Act to seek advice from Energex.

* Any costs incurred by Energex as a result of the works on the easement are to
be met by the property Developer / owner.

* This response does not constitute an approval to commence any works within
the easement. Consent to commence works relevant to the conditions of the
easement is required. All works on easement (including but not limited to
earthworks, drainage and detention basins, road construction, underground and
overhead services installation) require detailed submissions, assessment, and
consent (or otherwise) by Energex.

* All works proposed to be undertaken in close proximity to overhead or
underground electrical lines are to be undertaken in accordance with Energex’s
Works Practice Manual WP1323. This document refers to various standards,
guidelines, calculations, legal requirements, technical details, and other
information relevant to working near high voltage infrastructure. A copy of
WP 1323 can be found online via Energex's document library (Document library

Energex).

Should you require any further information on the above matter, please contact Harriet
Veal on 0427 293 604 or via email at [email protected].au-
Yours faithfully,
Warreet Veal
Harriet Veal
Town Planner

Have you seen our fact sheets?
See the ‘considerations when developing around electricity infrastructure’ section of our website

ww. energex.com au/referralagency

Page 7 of 8

Version: 4, Version Date: 19/01/2026

Page 8

                                                                              Appeal Rights
                                                                              PLANNING ACT 2016 & PLANNING REGULATION 2017




               Chapter 6 Dispute resolution                                                   (3) The appellant or, for an appeal to a tribunal, the registrar must,
                                                                                                  within the service period, give a copy of the notice of appeal to –
               Part 1 Appeal rights
                                                                                                  (a) the respondent for the appeal; and
               229 Appeals to tribunal or P&E Court
                                                                                                  (b) each co-respondent for the appeal; and
               (1) Schedule 1 of the Planning Act 2016 states –
                                                                                                  (c) for an appeal about a development application under schedule
                   (a) Matters that may be appealed to –
                                                                                                      1, table 1, item 1 – each principal submitter for the
                         (i)   either a tribunal or the P&E Court; or                                 development application; and
                         (ii) only a tribunal; or                                                 (d) for and appeal about a change application under schedule 1,
                                                                                                      table 1, item 2 – each principal submitter for the change
                         (iii) only the P&E Court; and
                                                                                                      application; and
                   (b) The person-
                                                                                                  (e) each person who may elect to become a co-respondent for the
                         (i)   who may appeal a matter (the appellant); and                           appeal, other than an eligible submitter who is not a principal
                                                                                                      submitter in an appeal under paragraph (c) or (d); and
                         (ii) who is a respondent in an appeal of the matter; and
                                                                                                  (f)   for an appeal to the P&E Court – the chief executive; and
                         (iii) who is a co-respondent in an appeal of the matter; and
                                                                                                  (g) for an appeal to a tribunal under another Act – any other
                         (iv) who may elect to be a co-respondent in an appeal of the
                                                                                                      person who the registrar considers appropriate.
                              matter.
                                                                                              (4) The service period is –
               (2) An appellant may start an appeal within the appeal period.
                                                                                                  (a) if a submitter or advice agency started the appeal in the P&E
               (3) The appeal period is –
                                                                                                      Court – 2 business days after the appeal has started; or
                   (a) for an appeal by a building advisory agency – 10 business
                                                                                                  (b) otherwise – 10 business days after the appeal is started.
                       days after a decision notice for the decision is given to the
                       agency; or                                                             (5) A notice of appeal given to a person who may elect to be a co-
                                                                                                  respondent must state the effect of subsection (6).
                   (b) for an appeal against a deemed refusal – at any time after the
                       deemed refusal happens; or                                             (6) A person elects to be a co-respondent by filing a notice of election,
                                                                                                  in the approved form, within 10 business days after the notice of
                   (c) for an appeal against a decision of the Minister, under chapter
                                                                                                  appeal is given to the person.
                       7, part 4, to register premises or to renew the registration of
                       premises – 20 business days after a notice us published under          231 Other appeals
                       section 269(3)(a) or (4); or
                                                                                              (1) Subject to this chapter, schedule 1 and the P&E Court Act, unless
                   (d) for an appeal against an infrastructure charges notice – 20                the Supreme Court decides a decision or other matter under this
                       business days after the infrastructure charges notice is given             Act is affected by jurisdictional error, the decision or matter is non-
                       to the person; or                                                          appealable.
                   (e) for an appeal about a deemed approval of a development                 (2) The Judicial Review Act 1991, part 5 applies to the decision or
                       application for which a decision notice has not been given –               matter to the extent it is affected by jurisdictional error.
                       30 business days after the applicant gives the deemed
                                                                                              (3) A person who, but for subsection (1) could have made an
                       approval notice to the assessment manager; or
                                                                                                  application under the Judicial Review Act 1991 in relation to the
                   (f)   for any other appeal – 20 business days after a notice of the            decision or matter, may apply under part 4 of that Act for a
                         decision for the matter, including an enforcement notice, is             statement of reasons in relation to the decision or matter.
                         given to the person.
                                                                                              (4) In this section –
               Note –                                                                             decision includes-
                   See the P&E Court Act for the court’s power to extend the appeal
                                                                                                  (a) conduct engaged in for the purpose of making a decision; and
                   period.
                                                                                                  (b) other conduct that relates to the making of a decision; and
               (4) Each respondent and co-respondent for an appeal may be heard
                   in the appeal.                                                                 (c) the making of a decision or failure to make a decision; and
               (5) If an appeal is only about a referral agency’s response, the                   (d) a purported decision; and
                   assessment manager may apply to the tribunal or P&E Court to
                                                                                                  (e) a deemed refusal.
                   withdraw from the appeal.
                                                                                                  non-appealable, for a decision or matter, means the decision or
               (6) To remove any doubt. It is declared that an appeal against an
                                                                                                  matter-
                   infrastructure charges notice must not be about-
                                                                                                  (a) is final and conclusive; and
                   (a) the adopted charge itself; or
                                                                                                  (b) may not be challenged, appealed against, reviewed, quashed,
                   (b) for a decision about an offset or refund-
                                                                                                      set aside or called into question in any other way under the
                         (i)   the establishment cost of trunk infrastructure identified in           Judicial Review Act 1991 or otherwise, whether by the
                               a LGIP; or                                                             Supreme Court, another court, a tribunal or another entity; and
                         (ii) the cost of infrastructure decided using the method                 (c) is not subject to any declaratory, injunctive or other order of
                              included in the local government’s charges resolution.                  the Supreme Court, another court, a tribunal or another entity
                                                                                                      on any ground.
               230 Notice of appeal
                                                                                              232 Rules of the P&E Court
               (1) An appellant starts an appeal by lodging, with the registrar of the
                   tribunal or P&E Court, a notice of appeal that-                            (1) A person who is appealing to the P&E Court must comply with the
                                                                                                  rules of the court that apply to the appeal.
                   (a) is in the approved form; and
                   (b) succinctly states the grounds of the appeal.                           (2) However, the P&E Court may hear and decide an appeal even if
                                                                                                  the person has not complied with the rules of the P&E Court
               (2) The notice of appeal must be accompanied by the required fee.




                                                                                                                                                    Page 8 of 8
Document Set ID: 24440260
Version: 4, Version Date: 19/01/2026

Used in these records

About this file

File size
446 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Approved Decision Notice - RAL25_0019 (As Published).pdf · 446 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.