Approved Decision Notice - RAL25/0019 (As Published)
Approved Plans
3. Development authorised by this approval must be undertaken generally in accordance with
the Approved Plans listed in the table/s below.
Plan No. Rev. Plan/Document Name Date
SP357720 Plan of Lots 3 -6 10.09.2025
4. All lot numbering on the subdivision plan to be submitted to Council for compliance
assessment must remain as shown on the Approved Plans.
Boundary Encroachments
5. Certification must be submitted to Council from a Registered Cadastral Surveyor (Qld) which
certifies that:
a. all constructed access and roadworks (including associated fill batters and retaining
walls) are fully contained within a dedicated reserve or registered easement
b. all utility services and connections (eg. electricity, telecommunications, water, sewerage)
are wholly located within the lot they serve or alternatively included within an easement
c. all existing effluent disposal areas are wholly located within the lot they serve and comply
with the boundary setback requirements of the Plumbing and Drainage Act 2002 and
associated codes and requirements
d. all dams (including ponded water, dam walls and associated spillway structures) are
wholly located within the boundaries of a single lot
e. all retaining walls and structures are fully contained within the lot they retain
f. any fill, including fill batters, are wholly contained within the subject site and not on
adjacent properties
Water & Sewer Connections
6. An underground connection to reticulated water and sewerage must be provided to each lot
in accordance with the standards and requirements of Northern SEQ Distributor–Retailer
Authority (Unitywater).
A Certificate of Completion from the Northern SEQ Distributor–Retailer Authority (Unitywater)
must be submitted to Council that certifies an underground connection to reticulated water
and sewerage has been provided to each lot.
Services
7. Underground reticulated electricity and telecommunication services must be provided to
each lot in accordance with an approval for Operational Works and the standards and
requirements of the relevant service provider.
8. Unless otherwise stipulated by telecommunications legislation at the time of construction, the
development must be provided with all necessary conduits, pits and pipes to accommodate
the future connection of optic fibre technology telecommunications.
9. Certification must be submitted to Council from all relevant service providers (Energex, NBN)
which certifies that the development has met the requirements of this Decision Notice and
all applicable legislation at the time of construction.
5. REFERENCE DOCUMENTS
Not applicable.
Page 2 of 8
Document Set ID: 24440260
Version: 4, Version Date: 19/01/2026
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Approved Decision Notice - RAL25/0019 (As Published).pdfRelated documentApplication case desk ↗
About this file
- File size
- 446 KB (small file)
- File type
No other editions are linked here.