30. All landscape works must be maintained generally in accordance with the approved design
for the life of the development.
Retention of Existing Vegetation
31. A Tree Management Plan in accordance with AS4970-2009 detailing vegetation in the
covenant to the north of the site (Cov. I SP182845). The TMP will demonstrate the Tree
Protection Zones and Structural Root Zones of vegetation in the covenant are protected, to
ensure the health and longevity of vegetation in the covenant. If impacts are proposed, offset
planting may be required for any impacted vegetation.
32. The report must be resubmitted to Council incorporating the above amendments prior to the
issue of any Development Permit for Operational Works.
33. Prior to the prestart meeting, a bank guarantee or a bond of $30,000 must be lodged as
security for the protection of the tree/s identified for retention in the conditions of this
approval. The bond:
a. may be drawn upon by Council in its entirety if any one tree identified for retention is
damaged to the point where the tree cannot be saved (as confirmed by the project
arborist and agreed in writing by Council)
b. will be returned upon practical completion of all the operational works relating to this
development.
34. The tree/s identified for retention in the conditions of this approval must be maintained in
good health for the life of the tree.
Environment
35. Prescribed Water Contaminants (as defined in the Environmental Protection Act 1994) must
not be released from the site or to waters within the site, or be likely to be released should
rainfall occur, unless all reasonable and practicable measures are taken to prevent or
minimise the release and concentration of contamination.
36. Erosion and sediment control measures must be installed and maintained to minimise
erosion on the site and to minimise the export of sediment and associated pollutants from
the site. The erosion and sediment control measures must be designed, installed and
maintained in accordance with current best practice standards
(*Refer to Advisory Notes).
37. Limit soil exposure on the site to a distance of no more than 2m beyond the extent of
earthworks shown on the approved plans except where the exposed soil is effectively
stabilised without delay and prior to rainfall occurring.
ENGINEERING/TRAFFIC
External Works
38. Hoffman Drive and the internal service road must be upgraded for the length of its frontage
to the subject site. The works must be undertaken in accordance with an Operational Works
approval and must include in particular:
a. Rectification of any damage to existing kerb and channelling; and
b. Construction of a pedestrian footpath in accordance with the conditions of this Decision
Notice.
Site Access and Driveways
39. A sealed access driveway must be provided from the internal service road to all parking and
manoeuvring areas of the development. The works must be undertaken in accordance with
an Operational Works approval and must include in particular:
a. a driveway crossover in accordance with Council’s standard drawing RS-051 and
respective addendum; and
Page 5 of 15
Document Set ID: 23565068
Version: 5, Version Date: 21/02/2025
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Minor Change Existing Approval MCU22 0038 02.pdfRelated documentApplication case desk ↗
About this file
- File size
- 323 KB (small file)
- File type
No other editions are linked here.