Council archive · source document
Development Application Part 3 of 3 - Plans · OPW11/0320
Plans and drawings: the text below has words only, no drawings.
is
r-
CONSTRUCTION MANAGEMENT PLAN
i
Objective To comply with all statutory regulations and relevant policies, and minimise the impact on the environment whilst carrying Construction 11. Implement the erosion and sedimentation control measures and associated management plan contained in
out construction activities in a safe and sustainable manner. Management the approved plans.
Tasks and Actions
Required 12. All earthwork stockpiles are to be kept moist, covered with tarpaulins or otherwise treated to minimise
dust emissions and stored in locations which minimise the possibility of the soil entering the stormwater
system.
To minimise the environmental and amenity impact of construction activities through onsite proactive approach to
Management 13. A construction shakedown area is to be installed at the entrance to the site to reduce unwanted soil
Strategy construction processes and consequences (cause and effect). Successful integration of activities will achieve ecological from leaving the site via vehicle tyres.
sustainability which is recognised as a balance that integrates the protection of ecological processes and natural systems, 14. All site staff and sub contractors shall be directed to use the nominated shakedown entry / exit
economic development, and maintenance of cultural, economic, physical and social wellbeing of people in communities. point.
15. Roads abutting the site and affected by the works shall be swept of regular intervals as required, or
whenever inspection shows signs of soil / pavement construction material on an abutting road or at the
nominated site entrance.
Construction The following schedule of management strategies, tasks and actions for construction works forms the basis of sustainable
Management 16. A high level of site "housekeeping" shall be maintained to ensure that vermin are not
management of site construction issues. Irrespective of whether or not an item is included in the following schedule
Tasks and Action attracted to poorly disposed of materials. Any waste or materials that have been
Required however, the Contractor shall employ best practice measures to achieve sustainable outcomes at all times.
illegally dumped on site shall be removed.
Management Strategy / Action
17. The Contractor shall provide bins for staff and sub contractors at locations where
1. Ensure that all staff and sub contractors working on the site are aware of potential environmental impacts and
food is consumed and shall ensure that such bins are used and emptied at regular
required minimum environmental control measures and responsibilities before commencement of any site works.
intervals.
2. Disturbance of soils below the canopy of any retained vegetation is to be excluded or otherwise minimised in
18. All materials, be they construction materials or used containers, shall either be
accordance with the approved plans.
recycled onsite or alternatively transported to a Council approved recycling station or
3. No dust emissions shall extend beyond the boundary of the site.
disposal point.
4. No odour emissions are detectable beyond the boundary of the site.
19. Any distillate or other petroleum products or dangerous goods stored onsite are
5. Work, including plant and equipment maintenance and servicing, shalt only be carried out between the hours of 630am
to be in bunded areas, located well clear of any watercourse. Appropriate spill
and 630pm Monday to Saturday inclusive. Written agreement must be provided by neighbouring residents if any work
control kits for any chemicals or stored fuels shall also be provided onsite.
activity with the potential to emit excessive noise is to be undertaken outside the above mentioned hours, and even with
20. Best practice management techniques shall be employed to control erosion and
such consent, such activities are to be minimised.
minimise sediment transport onsite, including those details contained in the approved
6. All equipment shall be acoustically treated with manufacturer supplied muffler systems with ensure that equipment
plans and the Erosion and Sedimentation Management Plan.
does not create environmental harm or excessive noise.
21. The Contractor shall prepare and implement an approved Traffic Management Plan
7. Temporary security lighting for the site must be designed and located to ensure that its effects are not obtrusive
for site construction activities. The Traffic Management Plan shall be provided to the
and direct light spill does not alter the amenity of adjacent properties.
Council inspector and the Supervising Engineer at the prestart meeting.
8. All existing utilities (roads, drainage, electrical and communication) on or adjacent the site are to be protected and
22. Comply with any conditions of Council's operational works approval applicable to
maintained at all times, with the cost of any damage to such infrastructure to be met by the Contractor.
the works.
9. Any areas of high risk / danger on the site are to be adequately signposted.
10. Vibration beyond the site boundary from construction activities is to be minimised and where there is a likelihood of
23. All public complaints received by the Contractor must be recorded in writing,
such vibration extending beyond the boundaries to an adjoining property owner, the property owner shall be advised
including any investigations undertaken, conclusions reached and actions taken as o
result of some. This complaints record is to be made available to the administering
accordingly.
authority on request.
24. All site personnel are to report any significant non-conformances to the site
manager as soon as practical and within 1 hour of the occurrence of, or
observance of same.
25. The contractor shall prepare an informative letter to be dropped to
residents/businesses adjacent to the development. The letter is to advise contact
details for communications for the site manager, working hours, projected timing of
works and any other information the contractor sees relevant.
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Development Application Part 3 of 3 - PlansRelated documentApplication case desk ↗
About this file
- File size
- 2.7 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.