IDAS form 20—Interfering with overland flow water and
construction or modification of a levee
(Sustainable Planning Act 2009 version 4.1 effective 1 October 2014)

This form must be used for development applications for operational work that involves:
     Interfering with overland flow water; or
     Construction or modification of a levee.
You MUST complete ALL questions that are stated to be a mandatory requirement unless otherwise identified on this
form.

For all development applications you must:
     complete IDAS form 1—Application details
     complete any other forms relevant to your application
    provide any mandatory supporting information identified on the forms as being required to accompany your
     application.
Attach extra pages if there is insufficient space on this form.

All terms used on this form have the meaning given in the Sustainable Planning Act 2009 (SPA) or the Sustainable
Planning Regulation 2009.

Note: If this development application involves a state resource, this application is not required to be supported by
evidence of resource entitlement. The allocation or entitlement to the resource is a separate process and should be
obtained prior to development commencing.

This form can also be completed online using MyDAS at www.dsdip.qld.gov.au/MyDAS

Mandatory requirements

1.     Are the works existing?

     No                  Yes—date constructed (if known)

2.     What is the nature of the proposed work? (Tick all applicable boxes.)

      Levee or levee bank                                              Storage
      Drainage works                                                   Other—specify below
      Embankment



3.     What is the purpose of the proposed work? (Tick all applicable boxes.)

      Flood mitigation
      Drain land
      Alteration, repair or extension of existing works
      Related to water supply
      Related to residential development
      Related to commercial, industrial or agricultural development
      Storage for watercourse water

Non-mandatory requirements
Full text of the other 2 pages

Page 2

                       Integrated Development Assessment System form
 4.      What are the details of the proposed construction materials (e.g. rock, earth, concrete)?

 Earth, rock, concrete

 5.      What are the details of the proposed construction method?

 Core filled concrete block retaining wall

 Mandatory supporting information

 6.      Confirm that the following mandatory supporting information accompanies this application

 Mandatory supporting information                                                     Confirmation of          Method of
                                                                                      lodgement                lodgement
 A sketch plan showing:
  the location of the proposed works and any existing works for levees or                Confirmed            Email
   interfering with overland flow water
     lot boundaries and descriptions                                                     Confirmed            Email

     existing works                                                                      Confirmed            Email
                                                                                          Not applicable
     the position of any watercourses or water bodies                                    Confirmed            Email
                                                                                          Not applicable
     the position of any roads                                                           Confirmed            Email
                                                                                          Not applicable
     the position of any area to be irrigated.                                           Confirmed
                                                                                          Not applicable
 Written documentation
 Hydrology report assessing the potential impact of the proposed works on any             Confirmed
 adjacent watercourse or water body and surrounding floodplain.
                                                                                          Not applicable
 A statement addressing the relevant part(s) of the State Development                     Confirmed
 Assessment Provisions (SDAP).                                                            Not applicable
 For an application involving assessable development for the construction or modification of a levee
 A hydraulic assessment including modelling to determine what changes in         Confirmed        Email
 water level, velocity and flow direction will occur as a result of constructing
 or modifying the levee.                                                         Not applicable
 A design report that outlines the description of the site, the nature and       Confirmed        Email
 extent of the works to be constructed or modified, construction
 considerations and operation and maintenance considerations.                    Not applicable

Privacy—Please refer to your assessment manager, referral agency and/or building certifier for further details on the
use of information recorded in this form.


OFFICE USE ONLY

 Date received                                              Reference numbers




                            IDAS form 20—Interfering with overland flow water and construction or modification of a levee or levee bank
                                                                                                         Version 4.1—1 October 2014

Page 3

   The Sustainable Planning Act 2009 is administered by the Department of State Development, Infrastructure and
   Planning. This form and all other required application materials should be sent to your assessment manager and any
   referral agency.




         Department of State Development, Infrastructure and Planning
         PO Box 15009 City East Qld 4002
         tel 13 QGOV (13 74 68)
         [email protected]
         www.dsdip.qld.gov.au




Department of State Development, Infrastructure and Planning
PO Box 15009 City East Qld 4002
tel 13 QGOV (13 74 68)          IDAS form 20—Interfering with overland flow water and construction or modification of a levee or levee bank
[email protected]
                                                                                                             Version 4.1—1 October 2014
www.dsdip.qld.gov.au

Used in these records

About this file

File size
146 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

IDASform20_DaintreeEstate.pdf · 146 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.