Attachment 7B - Fauna and Flora Assessment_NoosaLandfill_NorthernSection_Revision3
Native Foresters
Performance Outcomes Acceptable Outcomes Response
PO3 AO3.1 Complies with PO3
Development is designed and sited to manage Where clearing of vegetation cannot be practicably
adverse impacts on ecologically important avoided, the development: The landfill expansion works cannot be practicably
areas by: a) ensures the design and siting limits the avoided and have been minimised as much as
a) minimising the total footprint within loss of vegetation to the smallest extent
which all activities, buildings, possible;
possible.
structures driveways and other works b) protects and retains ecological values and
are contained; ecosystem processes to the greatest The proposed clearing will allow for the landfill
b) locating development in existing extent possible within and adjacent to the expansion to occur in accordance with the master
cleared areas or areas of low site; plan for the site, and will require clearing of 0.9
ecological value over other areas to c) provides measures to allow for safe hectares of mapped vegetation – area of biodiversity
the greatest extent possible; and movement of fauna through the site; and importance.
c) incorporating siting and design d) provides suitable habitat replacement and
measures to protect and retain replanting in accordance with PSP3 Clearing vegetation is unavoidable, but the following
ecological values and ecosystem Ecological Assessment Guidelines.
processes within or adjacent to the
is noted:
development site; and AO3.2 • The proposed clearing is directly adjacent
d) where adverse impacts have been Habitat trees, recruitment habitat trees, and roosting, to the existing cleared areas of the landfill
minimised, any residual impacts on breeding and feeding areas are protected for native site,
ecological values are compensated fauna habitat. • Vegetation proposed to be cleared is a
for through suitable habitat patch that is surrounded on three sides by
replacement and replanting on site in landfill areas and has been impacted by the
the first instance or in a way that
uses of the landfill,
results in a net gain and
enhancement of the overall habitat • Proposed works on the site include a HES
values of Noosa Shire. Basin and concrete crushing area which
are positioned to manage the expanded
landfill footprint and ensure stormwater
flows from the site are properly treated.
An offset plan for the cleared area has been
proposed and is detailed in Section 5.1 below.
PO4 AO4.1 Complies with PO4
Development provides for effective measures Vegetation is protected from disturbance or damage
during construction and operation to protect from The proposed clearing will be undertaken in
ecological values including: construction and operation activities by: accordance with a Construction Environmental
a) avoiding disturbance to or clearing of a) clearly marking trees to be retained with
vegetation in and within the vicinity of flagging tape;
Management Plan (CEMP) which will incorporate
the site; b) installing protective fencing around the actions specific to protecting the environmental
b) managing habitat disturbance and dripline of the vegetation and avoid filling values on site and adjacent to the site.
physical harm to fauna from noise, and excavating in these fenced areas;
Noosa Landfill & RRC – northern section – Fauna and Flora Assessment – REV3 31
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.