Decision Notice - MCU23-0129 & OPW23-0153 · MCU23/0129

of 16

Text shows just the words. Original shows the document exactly as it was published.

Check the original when the exact wording matters.

2311-37569 SRA

Attachment 1—Referral agency conditions

(Under section 56(1)(b){i) of the Planning Act 2016 the following conditions must be attached to any development
approval relating to this application) (Copies of the documents referenced below are found at Attachment 5)

 

 

No. | Conditions Condition timing
Development Permit for operational work

Schedule 10, Part 17, Division 3, Table 1, Item 1 — Tidal works or work within a coastal management
district —The chief executive administering the Planning Act 2016 nominates the Director-General of
the Department of Environment and Science to be the enforcement authority for the development to
which this development approval relates for the administration and enforcement of any matter relating

 

 

 

to the following conditions:
1. The development must be carried out generally in accordance with For the duration of
the following plans: works and to be

* ‘Site plan & water allocation plan’, prepared by The Jetty maintained
Specialist, dated 17/07/2023, drawing number TJS-04801-01,
version E

* ‘Layout plan’, prepared by The Jetty Specialist, dated
17/07/2023, drawing number TJS-04801-02, version E

* ‘Elevation’, prepared by The Jetty Specialist, dated
17/07/2023, drawing number TJS-04801-03, version D

 

 

2. The works to which this approval relates are to be for a private At all times
purpose only.

3. Any operator and contractor involved in the works to which this During construction
approval relates must:

(a) be provided a copy of referral agency conditions

(b) install all measures, plant and equipment necessary to
ensure compliance with the conditions of this approval

(c) maintain such measures, plant and equipment in a proper
and efficient condition

(d) operate such measures, plant and equipment in a proper
and efficient manner

4. For the proposed works only use maternal which are free from During construction

contaminants as defined under section 11 of the Environmental

Protection Act 1994.

5. Should the works become damaged as a result of erosion, flooding At all times

or storm tide inundation, the registered landowner(s) of the subject

land shall be responsible for the removal of all debris at their own

expense.

Schedule 10, Part 17, Division 3, Table 2, Item 1 — Tidal works or work within a coastal management

district —The chief executive administering the Planning Act 2016 nominates the Director-General of

the Department of Transport and Main Roads to be the enforcement authority for the development to

which this development approval relates for the administration and enforcement of any matter relating

 

 

 

 

 

 

to the following conditions:
6. The development must be carried out generally in accordance with At all times
the following plans:

* ‘Site plan & water allocation plan’, prepared by The Jetty
Specialist, dated 17/07/2023, drawing number TJS-04801-
01, version E

 

 

 

 

 

State Assessment and Referral Agency Page 3 0f8

Document Set ID: 22666179 Page 7 of 16

Version: 2, Version Date: 16/11/2023

Used in these records

About this file

File size
682 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Decision Notice - MCU23-0129 & OPW23-0153.pdf · 682 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.