Original source · versioned page text
Rfi - Scg 32225(L1)
27 February 2023
SCG Ref: 32225(L1)
By email: [email protected]
Noosa Shire Council
P.O. Box 141
TEWANTIN QLD 4565
ATTENTION: MS LISA PIENAAR
Dear Lisa
Re: MCU22/0196 & OPW22/0295 ~ Lots 2 & 3 MCH 3881, 130-132 Gympie Terrace Noosaville
We have reviewed Noosa Council’s request for information dated 8 December 2022 and provide our response to
the Engineering related items.
Issue 8 & 9: Basement Slab & Planters
The submitted documentation suggests that the basement planters are approximately 2.2-2.3m
below the existing natural ground level. It is unclear to Council if the proposed basement
slab extends underneath the proposed basement planters. Council is concerned that if the
planters are left ‘exposed’ without sufficient waterproofing from the basement slab,
groundwater may seep up into the planter box and be unable to drain from the basement.
Response:
The proposed basement slab and planters consist of structural design elements for the proposed building.
Detailed structural design for the building typically does not commence until planning and operational
works approval is granted. Building design information is assessed by the private building certifier in
accordance with the National Construction Code 2019 (NCC) and ABCB-2012.3 - Construction of
Building in Flood Hazard Areas. SCG as the design and responsible RPEQ, confirm the entire basement
will be fully tanked to ensure 1% flood immunity is maintained as required by the NCC.
Issue 10 & 11: Acid Sulphate Soils Management Plan
Pacific Geotech Consulting’s ACID SULFATE SOIL REPORT (PG-9236) dated November
2022 includes Acid Sulfate Soil Management recommendations for the development. A site-specific
Acid Sulfate Soil Management Plan, including a Dewatering Plan, has not been
included as part of the submitted documentation.
It is unclear to Council if SCG Consulting’s Earthworks Plan (32225-OW3.1) dated September
2022 has been amended to incorporate the constructional phase recommendations made in
Appendix E of Pacific Geotech Consulting’s ACID SULFATE SOIL REPORT (PG-9236) dated
November 2022.
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalFull text of the other 3 pages
Page 2
Response:
A Dewatering Management Plan (DMP) will be completed at detailed building design stage. We request
Council condition for this information to be provided prior to the prestart meeting. Please refer Appendix
E of Pacific Geotech’s Acid Sulphate Soil report (PG-9236) which, includes a site specific Acid Sulphate
Soil Management Plan.
Please see revised earthworks plan (SCG DRG 32225-OW3.1 Rev.A) to include reference to the Geotech
report by Pacific Geotech. We have also amended our earthworks planto nominate an approximate
stockpile location for treatment of Acid Sulphate Soil (ASS). However, it should be noted that the principle
contractor will ultimately determine the set-out of the site usage in accordance with their Construction
Management Plan. Additionally, due to the restricted space on site it would be assumed that stockpiles
of treated soils for re-use would not be kept on site. This may also result in ASS also being treated at a
off site location.
Issue 12 & 13: Earthworks
The submitted documentation states that the design and installation of the proposed
temporary concrete piling is to be done by ‘others’. Council has not received these plans or
details and is unable to assess the earthworks component of the application. Council is
concerned the proposed earthworks may undermine the structural integrity of the surrounding
lots (Lot 128 & 134 Gympie Terrace and Chaplain Park, Mill Street).
It is unclear from SCG Consulting’s Earthworks Plan (32225-OW3.1) dated September 2022
how the proposed pool excavations will take place from wholly within the subject site.
Response:
The proposed piling contract has not been awarded yet as a building as a contract will not be in place
until the structural design and building approval is granted. This information is assessed by the private
building certifier. SCG as the Structural and Civil RPEQ confirm all piling will be designed with appropriate
surcharge loading to ensure stability of all neighbouring structures are maintained. Ground anchoring will
not be permitted without written consent of the neighbouring property owner/s.
The primary focus of the construction of the temporary piling will be to maintain the stability of
neighbouring properties adjacent the excavation, that is why it’s speicified.
The programming of the pool constructions with regard to the construction program will be the
responsibility of the contracted builder. Our suggestion would be to construct the pools in unison with the
basement negating the need for adjacent allotment access. Regardless, it’s an issue which is resolved
prior to construction with the contracted builder (unknown at this stage) having due regard to all to all
neighbouring allotments.
Issue 14: Basement Seepage
Council recognise the finished floor level of the proposed basement is located beneath the
water table and is located in a low-lying, tidal area. Council is concerned that the basement
may experience seepage as a result.
Response:
The proposed basement slab and planters consist of structural design elements for the proposed building.
Detailed structural design for the building typically does not commence until planning and operational
works approval is granted. Building design information is assessed by the private building certifier in
accordance with the National Construction Code 2019 (NCC) and ABCB-2012.3 - Construction of
Building in Flood Hazard Areas. SCG as the Design RPEQ, confirm the entire basement will be fully
tanked to ensure 1% flood immunity is maintained as required by the NCC.
Issue 15: Sustainable Building Design Code
The proposed stormwater management plan does not include 3,000 litres of rain water storage
per dwelling as required by PO2 of the Sustainable Building Design Code.
SCG Consulting Engineers Page 2 of 4 SCG Ref:32225(L1)
Page 3
Response:
Please see revised stormwater management plan (SCG DDRG 32225-SW1.1 Rev A) to include a 3000lt
rain water storage for each dwelling to promote stormwater harvesting.
Issue 16 & 17: Stormwater Management
The submitted documentation references a ‘hydraulics consultant’ for the proposed internal
drainage. Council has not received plans or details from a ‘hydraulics consultant’ and is unable
to assess the stormwater component of the application as the submitted Stormwater
Management Plan does not contain sufficient information.
It is unclear from SCG Consulting’s Stormwater Management Plan (32225-SW1.1) dated
September 2022 where the proposed ‘150 grated drain’ will discharge to.
Response:
Roof drainage for the proposed building forms part of the building design and assessed by a private
building certifier in accordance with the NCC 2019 Volume 2. Detailed structural and internal hydraulic
design for the building design elements will commence after a development approval is in place.
As displayed on the Stormwater Management Plan (SCG Drawing No: 32225-SW1.1). The proposed “150
grated drain” discharges via a 150∅ PVC to the proposed GP1 stormwater pit.
Furthermore, we have added additional levels to internal drainage pits, as the proposed pipe runs are
considered very small and pipes grades are not an issues with the extent of filling required, we do not see
the need for a longitudinal section for each pipe, this has not been an issue in the past with Council on
similar scale developments. The proposed connection point for roof drainage has been nominated on the
proposed stormwater management plan.
Issue 18: Flooding
The subject site is located in Council’s Flood Hazard overlay and is adjacent to the Noosa
River and Canal. Council are concerned regarding the functionality of the proposed
stormwater system and associated infrastructure during, up to and including, 1% AEP events
at the end of the development’s lifespan. Council predict that the yearly average rainfall
will increase approximately 20% towards the end of the development’s life span (2100).
Response:
The proposed minimum Finished Floor Level (FFL) for the ground floor of the proposed building is
determined by Noosa Council at RL2.700 in order to achieve 1% AEP flood immunity for the year 2100
as per the flood information search from Noosa Council. This includes a 500mm freeboard for all habitable
space and thus Council has deemed sufficient to provide flood immunity to the building. Furthermore, the
proposed underground stormwater system (including kerb adaptors) is designed for minor drainage only
(10% AEP) in accordance with QUDM 2017. Council is questioning the functionality of the minor drainage
system for a major design storm which is not a design requirement in accordance with QUDM nor the
Noosa Council Planning Scheme. As the responsible RPEQ we confirm the overland flow (major drainage
design) for the site is sufficient that it will not cause flooding to any part of the building.
Issue 19: Onsite Maneuverability
Acceptable Outcome 12.2 of the Dual Occupancy and Multiple Dwelling Code states, where
located on any road of a higher order than local, vehicles must enter and leave the site in a
forward gear. The submitted documentation does not demonstrate that a B99 vehicle is able
to enter the Unit 2 garage carpark in a forward gear and manoeuvre on site without failure.
Response:
Please see revised vehicle maneuvering plan (SCG DRG 32225-OW5.1) attached to include additional
vehicle movements attached. As the certifying RPEQ, we did not foresee any issued relating to U2’s
garage and hence had shown the most restrictive maneuvers.
SCG Consulting Engineers Page 3 of 4 SCG Ref:32225(L1)
Page 4
Issue 20: Driveway Access
Council recognise that Gympie Terrace is a high-traffic area and are concerned vehicles
turning right into the subject site from Gympie Terrace may create unsafe traffic conditions.
Similarly, vehicles turning right from the subject site onto Gympie Terrace may have their
vision obstructed by a bus parked at the existing bus stop.
Response:
We have revised our driveway access plan (SCG DRG 32225-OW4.1) to include a left in left out access
only.
If you require any further information, please do not hesitate to contact our office.
Yours faithfully
TOM HARRINGTON – RPEQ 27698
For and on behalf of
SCG CONSULTING ENGINEERS
Enc SCG Drawings Numbers: 32225 – CS, OW1.1, OW2.1, OW3.1.A, OW3.2, OW4.1.A, OW4.2, OW4.3,
OW5.1.A, OW6.1, SW1.1.A, SW1.2
SCG Consulting Engineers Page 4 of 4 SCG Ref:32225(L1)