Rfi - Scg 32225(L1)

of 4

Page text shows just the words. Original shows the document exactly as it was published.

Response:
      A Dewatering Management Plan (DMP) will be completed at detailed building design stage. We request
      Council condition for this information to be provided prior to the prestart meeting. Please refer Appendix
      E of Pacific Geotech’s Acid Sulphate Soil report (PG-9236) which, includes a site specific Acid Sulphate
      Soil Management Plan.

         Please see revised earthworks plan (SCG DRG 32225-OW3.1 Rev.A) to include reference to the Geotech
         report by Pacific Geotech. We have also amended our earthworks planto nominate an approximate
         stockpile location for treatment of Acid Sulphate Soil (ASS). However, it should be noted that the principle
         contractor will ultimately determine the set-out of the site usage in accordance with their Construction
         Management Plan. Additionally, due to the restricted space on site it would be assumed that stockpiles
         of treated soils for re-use would not be kept on site. This may also result in ASS also being treated at a
         off site location.

Issue 12 & 13: Earthworks

         The submitted documentation states that the design and installation of the proposed
         temporary concrete piling is to be done by ‘others’. Council has not received these plans or
         details and is unable to assess the earthworks component of the application. Council is
         concerned the proposed earthworks may undermine the structural integrity of the surrounding
         lots (Lot 128 & 134 Gympie Terrace and Chaplain Park, Mill Street).
         It is unclear from SCG Consulting’s Earthworks Plan (32225-OW3.1) dated September 2022
         how the proposed pool excavations will take place from wholly within the subject site.

Response:
      The proposed piling contract has not been awarded yet as a building as a contract will not be in place
      until the structural design and building approval is granted. This information is assessed by the private
      building certifier. SCG as the Structural and Civil RPEQ confirm all piling will be designed with appropriate
      surcharge loading to ensure stability of all neighbouring structures are maintained. Ground anchoring will
      not be permitted without written consent of the neighbouring property owner/s.

        The primary focus of the construction of the temporary piling will be to maintain the stability of
        neighbouring properties adjacent the excavation, that is why it’s speicified.

        The programming of the pool constructions with regard to the construction program will be the
        responsibility of the contracted builder. Our suggestion would be to construct the pools in unison with the
        basement negating the need for adjacent allotment access. Regardless, it’s an issue which is resolved
        prior to construction with the contracted builder (unknown at this stage) having due regard to all to all
        neighbouring allotments.

Issue 14: Basement Seepage

         Council recognise the finished floor level of the proposed basement is located beneath the
         water table and is located in a low-lying, tidal area. Council is concerned that the basement
         may experience seepage as a result.

Response:
      The proposed basement slab and planters consist of structural design elements for the proposed building.
      Detailed structural design for the building typically does not commence until planning and operational
      works approval is granted. Building design information is assessed by the private building certifier in
      accordance with the National Construction Code 2019 (NCC) and ABCB-2012.3 - Construction of
      Building in Flood Hazard Areas. SCG as the Design RPEQ, confirm the entire basement will be fully
      tanked to ensure 1% flood immunity is maintained as required by the NCC.

Issue 15: Sustainable Building Design Code

         The proposed stormwater management plan does not include 3,000 litres of rain water storage
         per dwelling as required by PO2 of the Sustainable Building Design Code.




SCG Consulting Engineers                              Page 2 of 4                                   SCG Ref:32225(L1)
Log in to download the original file

RFI - SCG 32225(L1).pdf · 626 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.