Attachment B - Construction Methodology KANE
HOFFMAN DRIVE MEDICAL CENTRE
BASEMENT AND RETENTION WORKS
2. PROGRAMME & STAGING
A high level programme illustrating the proposed sequence of works is included in this submission as Appendix
A of this document. This programme broadly illustrates the sequence of construction activities and the critical path
for the works.
The general sequence of works is as follows:
Site establishment including temporary hoardings and site accommodation.
Pad preparation (at existing ground level) including imported material suitable to the piling equipment
Retention installation consisting of;
o Contiguous/secant piling to the Southern Boundary and Bunker enclosure – including temporary
rock anchors as required
o Sheet piling to the Northern, Eastern and Western boundaries
Bulk excavation works to the BEL as defined in the Civil Engineering plans
The programme provided is indicative only, and will be confirmed on completion of detailed design documentation.
PROGRAMME & STAGING PAGE 4 OF 13
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.