Attachment B - Construction Methodology KANE
HOFFMAN DRIVE MEDICAL CENTRE
BASEMENT AND RETENTION WORKS
3.2 TRAFFIC MANAGEMENT & PEDESTRIAN MOVEMENT
A detailed Traffic Management Plan is attached in Appendix B of this document. In preparing the Site
Establishment Plans, the following project specific risks have been taken into consideration:
PROJECT SPECIFIC PROPOSED RESPONSE CMP ADDRESSES
RISK/REQUIREMENT
Management of pedestrian Development of a detailed, Y
access around site. appropriate Pedestrian Strategy as a Refer Traffic Management
part of the project Traffic
Management Plan.
Traffic management including Development of a detailed Traffic Y
access to neighbouring Management Plan to ensure Refer Traffic Management
properties. appropriate access around site.
Offsite parking contractors. No Contractor parking is to be Y
provided during the proposed works. Refer ‘Contractor Parking’
Contractors will be encouraged to
make alternate arrangements for
accessing the site.
SUMMARY OF ANTICIPATED PROJECT PERMITS
Footpath Closure: No pedestrian access via the existing access easement will be permitted during the works.
It is not anticipated that the footpath at Hoffman Drive will be affected during the works.
Works Zone: NA – all works are to be completed within the site boundary.
Road Closure: Road Closures to complete the works are not proposed. Traffic Management at the private
easement will be used for hold and release purposes to ensure that access to neighbouring properties is
maintained at all times.
Out of Hours: It is not anticipated that works will be required to occur out of hours
Should any additional permits be required Kane Constructions will seek the necessary approvals through Noosa
Council.
ACCESS ARRANGEMENTS
There will be separate access points provide for the site. As outlined in Attachment A.
Pedestrian Access: Contractor access will be via a personnel gate adjacent Hoffman Drive. This will ensure
separation of workers from deliveries and overhead loading.
Vehicle Access (1): Piling/Retention works from the existing level will use a gated entry from the Access
Easement.
Vehicle Access (2): Following commencement of bulk excavations works, site access will be limited to a single
gated entry immediately adjacent the Hoffman Drive crossover.
SITE ESTABLISHMENT PAGE 7 OF 13
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.