                                                                                    HOFFMAN DRIVE MEDICAL CENTRE
                                                                                   BASEMENT AND RETENTION WORKS



3.2            TRAFFIC MANAGEMENT & PEDESTRIAN MOVEMENT
A detailed Traffic Management Plan is attached in Appendix B of this document. In preparing the Site
Establishment Plans, the following project specific risks have been taken into consideration:

    PROJECT SPECIFIC                   PROPOSED RESPONSE                         CMP ADDRESSES
    RISK/REQUIREMENT
    Management of pedestrian           Development of a detailed,                Y
    access around site.                appropriate Pedestrian Strategy as a      Refer Traffic Management
                                       part of the project Traffic
                                       Management Plan.
    Traffic management including       Development of a detailed Traffic         Y
    access to neighbouring             Management Plan to ensure                 Refer Traffic Management
    properties.                        appropriate access around site.

    Offsite parking contractors.       No Contractor parking is to be            Y
                                       provided during the proposed works.       Refer ‘Contractor Parking’

                                       Contractors will be encouraged to
                                       make alternate arrangements for
                                       accessing the site.



SUMMARY OF ANTICIPATED PROJECT PERMITS
Footpath Closure: No pedestrian access via the existing access easement will be permitted during the works.

It is not anticipated that the footpath at Hoffman Drive will be affected during the works.

Works Zone: NA – all works are to be completed within the site boundary.

Road Closure: Road Closures to complete the works are not proposed. Traffic Management at the private
easement will be used for hold and release purposes to ensure that access to neighbouring properties is
maintained at all times.

Out of Hours: It is not anticipated that works will be required to occur out of hours

Should any additional permits be required Kane Constructions will seek the necessary approvals through Noosa
Council.


ACCESS ARRANGEMENTS
There will be separate access points provide for the site. As outlined in Attachment A.

     Pedestrian Access: Contractor access will be via a personnel gate adjacent Hoffman Drive. This will ensure
      separation of workers from deliveries and overhead loading.
     Vehicle Access (1): Piling/Retention works from the existing level will use a gated entry from the Access
      Easement.
     Vehicle Access (2): Following commencement of bulk excavations works, site access will be limited to a single
      gated entry immediately adjacent the Hoffman Drive crossover.




SITE ESTABLISHMENT                                                                                     PAGE 7 OF 13
Log in to download the original file

Attachment B - Construction Methodology KANE.pdf · 2.5 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.