Issue – Earthworks
An earthworks plan has not been provided and therefore it is unclear the extent of earthworks required to be carried
out for the proposed development.
Information Required
15. Provide an Earthworks Plan demonstrating the extent of the proposed earthworks required to carry out the
proposed works. The additional plan must be prepared by a suitably qualified person (RPEQ – Registered
Professional Engineer of Queensland) and include, but not be limited to:
a. the extent and volume of cut and fill; and
Response: Refer attached sketch drawing M3024E EW01 A detailing extent and volume of cut and fill.
Approximate volume of cut of 497m3 and approximate volume of fill of 1m3 (based on a slab thickness of
200mm).
b. demonstrate the proposed earthworks will not adversely affect any structures within the adjoining
properties; and
Response: Refer Core Consulting advice attached to JFP information response. The Core Consulting advice
provides generic guidelines on temporary batter slopes, drainage & erosion control and QBCC Guide to
Preventing Structural Damage to be adopted during the building design and construction phase of the
development to ensure proposed earthworks do not adversely affect adjoining structures. Actual proposed
measures to ensure earthworks do not adversely affect adjoining structures will be prepared and submitted
to Council as part of the Building Application design and construct process by the appointed building
contractor.
c. demonstrate that all retaining structures, both temporary and permanent, both above and below ground, will
be contained entirely within the subject site.
Response: Refer Core Consulting advice attached to JFP information response. The Core Consulting advice
provides generic guidelines on footing and retaining wall design to be adopted during the building design
and construction phase of the development. Actual retaining wall design, both temporary and permanent,
above and below ground, contained entirely within the site will be prepared and submitted to Council as
part of the Building Application design and construct process by the appointed building contractor.
Please contact the undersigned if you wish to discuss any issues pertaining to this response.
Yours faithfully,
ANDREW FRASER
SENIOR ENGINEER (RPEQ 5691)
JFP URBAN CONSULTANTS
Encls: Amended Site Based Stormwater Management Plan (Revision B)
JFP Ref: M3024E-001 Page 3
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Attachment E_Engineering_Response.pdfRelated documentApplication case desk ↗
About this file
- File size
- 2.0 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.