Issue – Earthworks
An earthworks plan has not been provided and therefore it is unclear the extent of earthworks required to be carried
out for the proposed development.
Information Required
  15.     Provide an Earthworks Plan demonstrating the extent of the proposed earthworks required to carry out the
          proposed works. The additional plan must be prepared by a suitably qualified person (RPEQ – Registered
          Professional Engineer of Queensland) and include, but not be limited to:
          a. the extent and volume of cut and fill; and
               Response: Refer attached sketch drawing M3024E EW01 A detailing extent and volume of cut and fill.
               Approximate volume of cut of 497m3 and approximate volume of fill of 1m3 (based on a slab thickness of
               200mm).
          b. demonstrate the proposed earthworks will not adversely affect any structures within the adjoining
             properties; and
               Response: Refer Core Consulting advice attached to JFP information response. The Core Consulting advice
               provides generic guidelines on temporary batter slopes, drainage & erosion control and QBCC Guide to
               Preventing Structural Damage to be adopted during the building design and construction phase of the
               development to ensure proposed earthworks do not adversely affect adjoining structures. Actual proposed
               measures to ensure earthworks do not adversely affect adjoining structures will be prepared and submitted
               to Council as part of the Building Application design and construct process by the appointed building
               contractor.
          c. demonstrate that all retaining structures, both temporary and permanent, both above and below ground, will
             be contained entirely within the subject site.
               Response: Refer Core Consulting advice attached to JFP information response. The Core Consulting advice
               provides generic guidelines on footing and retaining wall design to be adopted during the building design
               and construction phase of the development. Actual retaining wall design, both temporary and permanent,
               above and below ground, contained entirely within the site will be prepared and submitted to Council as
               part of the Building Application design and construct process by the appointed building contractor.


Please contact the undersigned if you wish to discuss any issues pertaining to this response.

Yours faithfully,



ANDREW FRASER
SENIOR ENGINEER (RPEQ 5691)
JFP URBAN CONSULTANTS


Encls: Amended Site Based Stormwater Management Plan (Revision B)




JFP Ref: M3024E-001                                                                                           Page 3

Used in these records

About this file

File size
2.0 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Attachment E_Engineering_Response.pdf · 2.0 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.