Delegated Report - Code - Planning OPW22 0319 [As Published] · OPW22/0319

of 13

Text shows just the words. Original shows the document exactly as it was published.

Check the original when the exact wording matters.

                           -                     5      Landscape planting plan 3 of 3 by insite 10/01/2023
                                                        EMLA

                           -                     5      Plant palette + schedule by insite EMLA      10/01/2023

               CURRENCY PERIOD
               2.     The Currency Period for this development approval lapses if the development has not
                      substantially started by 27 April 2025, unless an application to extend the currency period is
                      approved by Council.
               PRIOR TO COMMENCEMENT OF WORKS
                      Engineering
               3.     The proposed trenching of Toolar Street must be done in accordance with Council’s Standard
                      Drawing RS-170.
               4.     To ensure the protection of Council’s assets during the works, Council requires the provision
                      of a bank guarantee of $10,000. The bond must be submitted to Council prior to the pre-start
                      meeting.
               5.     Bonds must:
                      a.       meet the requirements of council’s relevant Planning Scheme Policy for performance
                               and uncompleted works;
                      b.       be lodged with Council and accompanied by the Bond Administration Fee/s; and
                      c.       be requested for release by writing to Council, when relevant approval requirements
                               have been met.
                      Engineering
               6.     All necessary approvals from external service providers (e.g. Unitywater) and external parties
                      on which the development works are proposed have been obtained and a copy supplied to
                      Council.
               7.     A condition report including photographs of the frontage of the site must be completed and
                      submitted to council at the prestart meeting / prior to any works commencing. As part of the
                      condition report, include an assessment of the existing Council stormwater pit at the
                      proposed connection point.
               8.     Certificates demonstrating currency of public liability insurance and works insurance covering
                      the works must be submitted to Council prior to the prestart meeting.
               9.     Council must be contacted at least 5 working days prior to any works commencing to
                      organise a prestart. The contact number to arrange a pre-start meeting is 5329 6500. The
                      pre-start meeting must include the relevant parties for the following aspects of the works:
                      a.       Civil engineering works;
                      b.       Landscape works;
                      c.       Electrical reticulation works; and
                      d.       Other relevant parties
               10.    A Construction Management Plan must be submitted to Council prior to the pre-start meeting
                      and must specifically address the following:
                      a.       Traffic Management during all aspects of the construct phase including:
                               i.      A Traffic Management Control Plan in accordance with Manual of Uniform Traffic
                                       Control Devices (MUTCD) detailing all temporary signage and traffic control
                                       measures prior to construction;


                                                                                                         Page 5 of 13

Document Set ID: 22371387
Version: 5, Version Date: 28/04/2023


[OCR of page images]
- 5 Landscape planting plan 3 of 3 by insite 10/01/2023
EMLA

- 5 Plant palette + schedule by insite EMLA 10/01/2023

CURRENCY PERIOD

2. | The Currency Period for this development approval lapses if the development has not
substantially started by 27 April 2025, unless an application to extend the currency period is
approved by Council.

PRIOR TO COMMENCEMENT OF WORKS
Engineering

3. The proposed trenching of Toolar Street must be done in accordance with Council's Standard
Drawing RS-170.

4. Toensure the protection of Council’s assets during the works, Council requires the provision
of a bank guarantee of $10,000. The bond must be submitted to Council prior to the pre-start
meeting.

5. Bonds must:

a. meet the requirements of council’s relevant Planning Scheme Policy for performance
and uncompleted works;

b. be lodged with Council and accompanied by the Bond Administration Fee/s; and

Cc. be requested for release by writing to Council, when relevant approval requirements
have been met.

Engineering

6. — Allnecessary approvals from external service providers (e.g. Unitywater) and external parties
on which the development works are proposed have been obtained and a copy supplied to
Council.

7. — Acondition report including photographs of the frontage of the site must be completed and
submitted to council at the prestart meeting / prior to any works commencing. As part of the
condition report, include an assessment of the existing Council stormwater pit at the
proposed connection point.

8. Certificates demonstrating currency of public liability insurance and works insurance covering
the works must be submitted to Council prior to the prestart meeting.

9. Council must be contacted at least 5 working days prior to any works commencing to
organise a prestart. The contact number to arrange a pre-start meeting is 5329 6500. The
pre-start meeting must include the relevant parties for the following aspects of the works:

a. Civil engineering works;

b. Landscape works;

Cc. Electrical reticulation works; and
d. Other relevant parties

10. AConstruction Management Plan must be submitted to Council prior to the pre-start meeting
and must specifically address the following:

a. Traffic Management during all aspects of the construct phase including:

i. A Traffic Management Control Plan in accordance with Manual of Uniform Traffic
Control Devices (MUTCD) detailing all temporary signage and traffic control
measures prior to construction;

Page 5 of 13

Document Set ID: 22371387
Version: 5, Version Date: 28/04/2023

Used in these records

About this file

File size
893 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Delegated Report - Code - Planning OPW22 0319 [As Published].pdf · 893 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.