Council archive · source document
Delegated Report - Code - Planning OPW22 0319 [As Published] · OPW22/0319
ii. Maintenance of safe vehicle and pedestrian access across the frontage of the
site both during daily construction and after daily construction has ceased;
iii. Proposed fencing to the site during the construction phase of the development;
and
iv. Adequate parking arrangements for construction workers.
b. Maintenance and protection of water quality and existing drainage lines through the
construction site through the implementation of appropriate erosion and sediment
control measures;
c. Works programme identifying key components of the works and their respective
durations;
d. Establishment of a communication protocol with the general public, adjoining owners,
emergency services and local businesses to advise of agreed construction times,
impacts on traffic and services and other relevant issues;
e. Include a post out to the local residents and businesses advising of the proposed
development, the expected time frames and the site contact details;
f. Include signage in prominent locations on the boundaries of the site advising of the
proposed development, the expected time frames and the site contact details; and
g. identification of complaint management procedures including:
i. contact details for the on-site manager; and
ii. dispute resolution procedures.
11. Any changes to the details associated with the supervising RPEQ or Principal Contractor
during construction, must be notified to council in writing within five business days of the
change occurring.
12. Any conflict between the development and an existing or proposed service must be referred
to the relevant service authority for determination prior to commencement of works.
DURING CONSTRUCTION
Engineering
13. The developer must meet any costs to repair damage to any Council asset during
construction, where damage is a result of the development works. Damage to assets must
be repaired immediately where it creates a hazard to the community. In circumstances where
the damage does not create a hazard to the community, it must be repaired immediately on
completion of the works associated with the development.
14. All works must be supervised by a Registered Professional Engineer of Queensland (RPEQ)
who is independent of the Developer and Principal Contractor, and they must certify that all
works conform to the Operational Works permit. Where municipal works are involved, such
confirmation must be submitted for the respective hold points prior to any site inspection by
Council Officers.
15. All works must be constructed and work procedure undertaken in accordance with:
a. The approved plans/documents and conditions detailed in this Decision Notice;
b. The relevant conditions of the higher order Material Change of Use/Reconfiguration of
Lot approval MCU21/0083 to which this approval relates;
c. All relevant Noosa Council Planning Scheme Policies, standard drawings, standard
specifications and guidelines; and
d. The latest version of the Healthy Waterways document “Water Sensitive Urban Design
Technical Design Guidelines for South East Queensland” for all water quality devices
to be constructed on site.
Page 6 of 13
Document Set ID: 22371387
Version: 5, Version Date: 28/04/2023
[OCR of page images]
ii. Maintenance of safe vehicle and pedestrian access across the frontage of the
site both during daily construction and after daily construction has ceased;
iii. | Proposed fencing to the site during the construction phase of the development;
and
iv. Adequate parking arrangements for construction workers.
b. Maintenance and protection of water quality and existing drainage lines through the
construction site through the implementation of appropriate erosion and sediment
control measures;
Cc. Works programme identifying key components of the works and their respective
durations;
d. Establishment of a communication protocol with the general public, adjoining owners,
emergency services and local businesses to advise of agreed construction times,
impacts on traffic and services and other relevant issues;
e. Include a post out to the local residents and businesses advising of the proposed
development, the expected time frames and the site contact details;
f. Include signage in prominent locations on the boundaries of the site advising of the
proposed development, the expected time frames and the site contact details; and
g. identification of complaint management procedures including:
i. contact details for the on-site manager; and
ii. dispute resolution procedures.
11. Any changes to the details associated with the supervising RPEQ or Principal Contractor
during construction, must be notified to council in writing within five business days of the
change occurring.
12. Any conflict between the development and an existing or proposed service must be referred
to the relevant service authority for determination prior to commencement of works.
DURING CONSTRUCTION
Engineering
13. The developer must meet any costs to repair damage to any Council asset during
construction, where damage is a result of the development works. Damage to assets must
be repaired immediately where it creates a hazard to the community. In circumstances where
the damage does not create a hazard to the community, it must be repaired immediately on
completion of the works associated with the development.
14. All works must be supervised by a Registered Professional Engineer of Queensland (RPEQ)
who is independent of the Developer and Principal Contractor, and they must certify that all
works conform to the Operational Works permit. Where municipal works are involved, such
confirmation must be submitted for the respective hold points prior to any site inspection by
Council Officers.
15. All works must be constructed and work procedure undertaken in accordance with:
a. | The approved plans/documents and conditions detailed in this Decision Notice;
b. | The relevant conditions of the higher order Material Change of Use/Reconfiguration of
Lot approval MCU21/0083 to which this approval relates;
Cc. All relevant Noosa Council Planning Scheme Policies, standard drawings, standard
specifications and guidelines; and
d. The latest version of the Healthy Waterways document “Water Sensitive Urban Design
Technical Design Guidelines for South East Queensland” for all water quality devices
to be constructed on site.
Page 6 of 13
Document Set ID: 22371387
Version: 5, Version Date: 28/04/2023
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Delegated Report - Code - Planning OPW22 0319 [As Published].pdfRelated documentApplication case desk ↗
About this file
- File size
- 893 KB (small file)
- File type
No other editions are linked here.