8.4. Low impact construction techniques are used around vegetation to minimise
interference with the vegetation.
9. Cleared vegetation is to be suitably processed by one of the following methods and removed
from the site:
9.1. Processing through a woodchipper or shredder. The resulting mulch is to be
stockpiled loose in heaps of less than 1000 cubic metres, less than 2.5 metres high
with a minimum of 10 metres between edges of heaps.
9.2. Disposal for firewood.
9.3. Disposal for landscaping purposes.
9.4. Transport to alternative site for breaking down materials provided that all necessary
permits have been obtained to allow the alternate site to be used for this purpose.
9.5. The applicant is advised that burning off is an unacceptable method of disposal.
10. A minimum of 20% of the site shall be retained as soft landscaping
General
11. Buildings and structures (including swimming pools, sheds, or outbuildings) shall not be
constructed under overhead electricity transmission lines, or within any easements.
12. The development must be undertaken and operated in a manner that causes no detrimental
effect upon the amenity of the neighbourhood by reason of the creation of excessive noise,
lighting nuisance or other emissions.
13. All hot water systems installed shall be either solar systems; electric heat pump systems; or
gas systems (LPG or natural).
14. External colours and finishes of the building shall comprise of muted/environmental tones
that blend with the natural environment.
15. Gates must not be installed along the rear property boundary.
Demolition or Relocation of Existing Dwelling
16. Infrastructure including reticulated water, sewerage, stormwater, and electricity are to be
protected from damage and made safe to the standard required by the regulatory authority.
17. All infrastructure must be disconnected, capped or sealed including:
17.1. electricity meters removed and electrical wires disconnected; and
17.2. telephone lines are disconnected; and
17.3. high speed data cables and television provider boxes are disconnected and
removed to the standard required by the regulatory authority
18. All building materials containing asbestos, including asbestos cement sheeting or roofing
and lagging, must be removed from the building and disposed of in accordance with industry
best practice.
19. Waste generated during construction must be stockpiled in a centralised location and
covered as required to prevent material being blown onto adjoining properties including the
road reserve or food waste from generating vermin. All site waste must be disposed of to an
approved waste disposal facility either directly or via an approved waste receptacle and
collection service. Storage areas are to be located near the temporary access to the site so
that access can be gained with out damage to infrastructure.
20. All building materials containing asbestos products must be disposed on in accordance with
industry best practice.
Page 3 of 10
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
SUPERSEDED Decision Notice - 010.2009.00000879.001 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 69 KB (small file)
- File type
No other editions are linked here.