Response to Information Request 10-6-2025 Traffic management plan · OPW25/0042

Plans and drawings: the text below has words only, no drawings.

Log in to see the plans as drawn
Traffic Management Plan – 25040286

   8.4 Implementing Traffic Guidance Schemes

As detailed by the MUTCD, AGTTM and The Code all personnel who install or dismantle TGS shall hold a
current Implement Traffic Guidance Scheme qualification. All traffic guidance schemes are implemented under
AGTTM Part 5 Short Term Low Impact Work sites or as described on the TGS and will generally follow the below
approach.

   8.4.1   Implementation a TGS

           •   Determine points of reference and conduct a site-based
               risk assessment.
           •   Install detours (if required) (e.g. setup detour prior to
               closing road).
           •   Sign upside roads (if required) either sequentially,
               before or after the road being worked on.
           •   Install signs on the road being worked on, taking into
               account Lateral Shift or Contra-Flow, implement setup
               on non-works side of the roadway first.
           •   Cover pre-existing conflicting signs as you go.
           •   Install remaining on road devices (e.g. cones, bollards,
               delineators). `
           •   Perform implementation check (e.g. drive through).



   8.4.2   Remove TGS

           •   Confirm work has ceased and ensure workers, plant
               and equipment are off the roadway.
           •   Clear the road being worked on of devices (lateral
               shift, contraflow must be removed, work area side 1st)
           •   Remove implemented signage from the road being
               worked on. Work area is able to be opened to traffic.
           •   Reinstate pre-existing signage.
           •   Clear side roads of devices, signs and detour signs
               and open side roads.




               Document MSF-AT-TMP-001| Issued 05 September 2024| Review: 05 September 2025| Owner: Trevor Leggett | Page: 34
                                      [UNCONTROLLED IF WHEN PRINTED AFTER 05 September 2024]

Used in these records

About this file

File size
1.3 MB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Response to Information Request 10-6-2025 Traffic management plan.pdf · 1.3 MB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.