Response to Information Request 10-6-2025 Traffic management plan · OPW25/0042

Plans and drawings: the text below has words only, no drawings.

Log in to see the plans as drawn
Traffic Management Plan – 25040286

   8. IMPLEMENTATION
   8.1 Communicating TMP Requirements

Prestart meeting to include requirements of the TMP – which stage of the works are going to be undertaken
and which TGS to be used. All Traffic Management crew are to sign on acknowledging their awareness of the
requires of the TMP and the planned works for each shift.

   8.2 Traffic Guidance Schemes

The Traffic Guidance Scheme (TGS) outlined in 15 Appendix A TRAFFIC GUIDANCE SCHEMES and listed
below have been provided for the following stages to demonstrate the type of controls that will be implemented
throughout the term of the contract. All sign and device requirements are shown on each TGS. Should the use
of additional (not shown on the TGS or listing of devices) or reduced number of devices be required due to
unforeseen needs, they shall be recorded within the Daily Diary as a variation to the TMP, following prior
approval.

                              Traffic
    Construction
                            Management                      TGS Number and version                                   Details
      Stages
                              Stages

      Stage 1                      1                    25040286-TGS 01-TT-HR-CMI-                     Trucks Turning Hold & Release
                                                        Serenity Close_Noosa Heads-R0




   8.3 Sequence and Staging

The sequence of temporary traffic management installation, work activities and temporary traffic management
removal are shown in the table below.

                Step          Details


                   1          Prestart meeting

                   2          Implement TGS

                   3          Drive through site to ensure implementation is correct Works not to commence until this
                              has been completed

                   3          Ingress of plant and equipment

                   4          Complete works

                   5          Egress of plant and equipment

                   6          Remove TGS in reverse order to the Implementation.

                   8          Drive Through Site to ensure all Temporary Traffic Management Devices have been
                              removed and all regulatory signage has been reinstated.




                Document MSF-AT-TMP-001| Issued 05 September 2024| Review: 05 September 2025| Owner: Trevor Leggett | Page: 33
                                       [UNCONTROLLED IF WHEN PRINTED AFTER 05 September 2024]

Used in these records

About this file

File size
1.3 MB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Response to Information Request 10-6-2025 Traffic management plan.pdf · 1.3 MB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.