Response to Information Request 10-6-2025 Traffic management plan · OPW25/0042

Plans and drawings: the text below has words only, no drawings.

Log in to see the plans as drawn
Traffic Management Plan – 25040286

   10.         MONITORING AND MEASUREMENT
   10.1        Daily Inspections

Prior to works commencing the Site Supervisor shall communicate the Traffic Management Plan to all key
stakeholders and affected parties.

On completion of setting out the traffic control measures; the site is to be monitored for a suitable period of
time. If traffic speeds on the approaches to the work site are assessed as being above the temporary posted
speed zone for the work site, the Site Supervisor is to initiate action to modify the approach signage and
tapers in accordance with the requirements of AGTTM/CoP. All such actions are to be recorded in the Daily
Diary. Should road users be observed to continue to travel in excess of the posted speed limit, the police may
be requested to attend the site to enforce the temporary posted speed limit.

The Traffic Management Design accredited supervisory person at the worksite may conditionally approve
changes made to a complex traffic management plan subject to review and endorsement of the change by an
RTM as soon as practicably possible.

The Traffic Management Contractor shall ensure that all temporary signs, devices and controls are maintained
at all times. To achieve this, procedures in line with the requirements outlined in AGTTM Part 6 will be
instituted. The monitoring program shall incorporate inspections:
     Before the start of work activities on site,
     During the hours of work,
     Closing down at the end of the shift period, and
     After hours.


A daily record of the inspections shall be kept indicating.
     When traffic controls where erected,
     When changes to controls occurred and why the changes were undertaken,
     Any significant incidents or observations associated with the traffic controls and their impacts on road
          users or adjacent properties.


The Traffic Management Contractor shall ensure that personnel are assigned to monitor the traffic control
scheme. Inspections shall at least satisfy the following requirements.

   10.1.1 Before works start

     Confirm TMP and TGS are suitable for the day’s activities.
     Inspect all signs and devices to ensure they are undamaged, clean and comply with the requirements
        depicted on the TGS.
     After any adjustments have been made to the signs and devices, conduct a drive through inspection to
        confirm effectiveness.

   10.1.2 During work hours

     Designate and ensure that appropriate work personnel drive through the site periodically to inspect all
        signs and devices and ensure they are undamaged and comply with the requirements depicted on the
        Traffic Guidance Schemes.
     Attend to minor problems as they occur.




               Document MSF-AT-TMP-001| Issued 05 September 2024| Review: 05 September 2025| Owner: Trevor Leggett | Page: 40
                                      [UNCONTROLLED IF WHEN PRINTED AFTER 05 September 2024]

Used in these records

About this file

File size
1.3 MB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Response to Information Request 10-6-2025 Traffic management plan.pdf · 1.3 MB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.