Decision Notice - 010.2008.00001867.001 [As Published] · 132008.1867
2008/1867
A duly executed copy of the easement shall be submitted to Council for perusal prior to the
use commencing.
Any changes required by Council’s Solicitor must be corrected immediately.
36. No building or other structure shall be constructed or encroach over an easement.
Earthworks
37. Earthworks on site shall be carried out in accordance with Council’s Planning Scheme Policy
PSP5 – Engineering Design Standards, so as not to cause the additional ponding of water on
any adjoining lands or the blockage of, or interference with, any natural watercourses. Detailed
site surveys indicating natural surface levels and contours of the adjoining properties must be
provided with the application for a Development Permit for Operational Works for Drainage.
This may require the design and construction of drainage pipes and/or an overland flow-path
within the development site that caters for drainage from the adjoining sites for a design storm
with an Average Recurrence Interval of 1 in 100 years. A private easement for the Drainage of
Water encompassing the drainage pipes or overland flow-path will also be required. In this
regard a Development Permit for Operational Works shall be obtained.
Should evidence be provided to Council indicating that no additional ponding of stormwater
will occur on the adjoining properties the requirement for the drainage pipes, overland flow-
path and easement shall not apply.
38. Earthworks carried out on site shall not affect the structural integrity of any of the existing
fences or structures that border the development site. Fences that are affected shall be
replaced prior to the Building Certifier issuing the Certificate of Classification. In this regard
any fences to be replaced shall be clearly shown on the plans submitted for Operational
Works approval.
Erosion and Sediment Control
39. Any person acting on this permit shall prevent erosion and sediment export from leaving the
site. Site control measures such as silt fencing, controlled gravel access to the site and
controlled disposal of waste, will be necessary.
In this regard plans detailing the methods of controlling erosion and sediment are required to
be submitted to the Council for approval prior to obtaining a Development Permit for
Operational Works.
40. Scour of the site shall not occur as a result of the approved development. In this respect, all
overland flow path areas must be suitably stabilised.
Contributions Towards Council Infrastructure
41. Monetary contributions shall be paid to Sunshine Cost Regional Council towards the cost of
providing and/or upgrading various infrastructure at the rates applicable at the time of
payment. An estimate only of the contribution amounts under the current Council policies and
requirements is outlined in the table below:
Contribution Required For: Amount:
PSP12 – Public Open Space Contributions (Park) $ 3,164
PSP16 – Sewerage Headworks Contributions $3,513
PSP17 – Water Supply Headworks Contributions $4,956
PSP20 – Pathway Trunk Network Contributions $ 711
TOTAL Contribution Amount = $ 12,344
Page 6 of 14
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Notice - 010.2008.00001867.001 [As Published]Related documentApplication case desk ↗
Decision Notice - 010.2008.00001867.001 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 83 KB (small file)
- File type
No other editions are linked here.