SPECIAL MEETING MINUTES 27 JANUARY 2021
Car parking
11. 56 additional car spaces must be provided prior to the commencement of
the use of the playground. The car parking is to be provided in the following
manner:
a. Lower Mill Road (22 additional formally sealed and line-marked
spaces)
b. Maple Street road reserve (12 formally sealed and line-marked
spaces)
c. Southern side of Mary River Road west of the tennis courts (22
spaces) be constructed as an overflow parking area.
12. The overflow parking area must be monitored for a full week in school
holidays and a full week outside of school holidays after the playground
has been fully operational for three months (and again at six months). The
results of the surveys must be provided to Council’s Manager Development
Assessment.
13. The overflow parking area must be formally sealed and line-marked if
regular use is identified at either period of monitoring referred to in
Condition 11.
14. The parking on the southern side of Marara Street must be amended as
follows:
a. The three (3) parking spaces closest to the existing disabled parking
spaces must be signed as being for 15 minute parking.
b. Three (3) months after that change has been implemented, usage
should be reviewed to determine whether the number of 15 minute
spaces (for short duration library trips) should be increased or
decreased to meet demands.
c. The remaining four (4) parking spaces in that existing 2 hour parking
zone be clearly signed as being for library use only.
Soil Contamination
15. Prior to the commencement of the use of the playground:
a. A Remediation Action Plan must be prepared and submitted to
Council which includes the following actions:
i. Provision of a Waste Acceptance Letter from an approved
waste management facility
ii. Excavation of approximately 30 m3 of impacted
TCDD/PCDD/F in the vicinity of BH27 for temporary stockpiling
and disposal.
iii. Following excavation/remedial excavation works, at least of 8
validation samples (including Quality Assurance/Quality
Control) must be collected from base of the excavation and
stockpile of excavated material.
iv. Validation samples must be analysed for presence of
TCDD/PCDD/F by an approved laboratory analyst.
v. A Quality Assurance/Quality Control program must be
implemented as part of the laboratory analysis.
Page 7 of 10
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.