Lot 22 Medihub RFI Response · OPW22/0303

of 2

Text shows just the words. Original shows the document exactly as it was published.

Continued:

    5. Excavation of the basement to the underside of capping beam level.
    6. Bracing installed to support the structure during construction.




    7. Excavation to be continued in approximately 2-3m increments to allow steel and shotcrete
       to be installed.




    8. Repeat methodology until underside of bottom basement slab RL is reached.




NOTE:

This methodology does not incorporate any anchors within the site or encroaching into neighboring
properties. It will not have any adverse effect on adjoining infrastructure, buildings or vegetation.

Used in these records

About this file

File size
655 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Lot 22 Medihub RFI Response.pdf · 655 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.