Original source · versioned page text
7. Appendix D - SPP SDAP Checklists and Assessment Benchmarks
Performance outcomes Acceptable outcomes Response
it is recommended that an RPEQ
certified traffic impact assessment is
provided.
Further information on how to
prepare a traffic impact assessment
is provided in the Guide to Traffic
Impact Assessment,
Department of Transport and Main
Roads, 2017.
PO4 Development does not impose AO4.1 The layout and PO4 Complies
traffic loadings on a state-controlled design of the development The proposed development
road which could be accommodated directs traffic generated by is not located in close
on the local road network. the development to the proximity to a state-
local road network. controlled road.
PO5 Upgrade works on, or AO5.1 Upgrade works on a PO5.1 Not Applicable
associated with, a state-controlled state-controlled road are Proposed upgrade works
road are built in accordance with designed and constructed are not proposed.
relevant design standards. in accordance with the
Road Planning and Design
Manual, 2nd edition,
Department of Transport
and Main Roads, 2016.
PO6 Development involving the AO6.1 Fill, extracted AO6.1 Complies
haulage of fill, extracted material or material and spoil material Any fill, extracted material
excavated spoil material exceeding is not transported to or from and spoil material will not
10,000 tonnes per year does not the development site on a be transported to or from
damage the pavement of a state- state-controlled road. the development site on a
controlled road. state-controlled road.
Note: It is recommended that a
transport infrastructure impact
assessment and pavement impact
assessment are provided.
Further information on how to
prepare a traffic impact assessment
is provided in the Guide to Traffic
Impact Assessment, Department of
Transport and Main Roads, 2017.
PO7 Development does not AO7.1 Development does AO7.1 Complies
adversely impact on the safety of a not require a new railway The proposed development
railway crossing. crossing. does not require a new
railway crossing.
Note: It is recommended that a OR
traffic impact assessment be
prepared to demonstrate AO7.2 A new railway AO7.2 Not applicable
compliance with this performance crossing is grade The proposed development
outcome. An impact on a level separated. complies with AO7.1.
crossing may require an Australian
Level Crossing Assessment Model OR all of the following AO7.3 Not applicable
(ALCAM) assessment to be acceptable outcomes The proposed development
undertaken. Section 2.2 – Railway apply: complies with AO7.1.
17
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the original