Original source · versioned page text
2020-07-16-sm-agenda-item-1-attachment-5-final-noosa-plan-2020-part-8-10-schedules-appendix
The original of this document is very large (19.9 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.
This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).
Log in to see the plans as drawn Column 1 Column 2 Column 3 Column 4
Map reference Trunk infrastructure Estimated timing Establishment cost5
Upgrade roundabout capacity
R6 Tewantin, Butler St / Poinciana
Ave 2021 2026 $574,919
Upgrade roundabout capacity
R7 Peregian Beach, Heron St /
David Low Way 2021 2026 $212,106
Upgrade roundabout capacity
R8 Peregian Beach, David Low Way
/ Lowry St / Peregian Esplanade 2021 2026 $719,851
Upgrade 4 way intersection to
roundabout
R9 Noosaville, Walter Hay Dr /
Eenie Creek Rd 2021 2026 $199,551
Upgrade roundabout capacity
R10 Noosaville, Walter Hay Dr / $28,750
Eumundi Noosa Rd 2021 2026
Upgrade roundabout capacity
R11 Sunshine Beach, Ben Lexcen Dr 20212026 $2,128,215
/ Eenie Creek Rd
Upgrade signalised intersection
R12 Noosaville, Eumundi Noosa Rd / 20212026 $338,952
Eenie Creek Rd
Upgrade roundabout capacity
R13 Noosaville, Reef St / Mary St 20212026 $425,823
Upgrade roundabout capacity
R14 Cootharaba, Wapunga Lane 20262031 $1,037,592
(Bridge)
Upgrade one lane bridge to two
lane bridge re Safety Issues
R15 Noosaville, Gympie Tce – 20172018 $696,730
Eumundi Rd/Gibson Rd
roundabout to Cloudsley St. Incl.
Hilton Tce/Gympie Tce
roundabout.
R16 Noosaville, Weyba Rd – Leslie 20172018 $1,490,790
Dr. to Reef St
R17 Noosa Heads, Noosa Parade – 20202022 $5,791,400
full corridor upgrade to achieve
improved bicycle safety and bus
transit.
R18 Tewantin, Cooroy Noosa Rd / 20162017 $95,138
Beckmans Rd intersection
Improvements to the existing ‘T’
intersection for cycling safety
R19 Tewantin, Cooroy Noosa Rd, 20162017 $2,442,448
Upgrading to include bike lands
R20 Castaways Beach, David Low 2018/2019 $236,500
Way
Safety Improvements at
Castaways Carpark
NOOSA PLAN 2020 Page 13 of 73
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.