              (xiv)   relevant management practices, including flood warning and evacuation measures;
              (xv)    details of any easements or reserves required for stormwater design; and
              (xvi)   details of detention/retention storages.

 (5)    The level of detail required for a particular development application should be determined in consultation with Council’s
        development assessment officers.


 SC6.9.6              Landslide

 (1)    Where a development is subject to the Landslide hazard overly code, a well made application will include a geo­technical, and
        management plan including the impacts of mitigation techniques on flora and fauna.
 (2)    A site specific geo­technical analysis prepared by a registered professional engineer:
        (a)   identifying any potential stability and associated problems including—
              (i)     long­term stability of the site; and
              (ii)    any potential adverse effects by landslides originating on sloping land above the site;
              (iii)   long­term stability of the proposed development; and
              (iv)    access to the site in the event of a landslip; and

        (b)   detailing proposed methods of addressing any identified potential stability and associated problems.

 SC6.10 ­ PSP9                 Waste Management
 SC6.10.1             Purpose

 (1)    The purpose of this planning scheme policy is to provide guidance to applicants on:
        (a)   the application of the Waste Management Code in the Noosa Plan;
        (b)   the preparation and assessment of waste management plans;
        (c)   design criteria for waste management including minimum service levels for types of development, size and appearance of
              waste storage areas, and vehicular access standards associated with development;
        (d)   the provision of efficient, safe, hygienic and sustainable waste management practices that meet the needs of occupants,
              contractors and minimises environmental nuisance to neighbours; and
        (e)   the proper consideration of waste minimisation and waste separation to so that materials can be recycled and reused in
              developments.


 SC6.10.2             Preparing a waste management plan

 (1)    A waste management plan is a document that details the type and quantity of waste material that is likely to be generated from a
        particular development site. The document also details where and how the waste should be stored, how waste will be disposed
        and procedures for handling the waste.
 (2)    A waste management plan is required where the development has the potential to generate significant quantities of waste or
        waste that is of a hazardous nature and should have a waste management plan as part of the information required to assess the
        application.
 (3)    The following is a list of developments which must have a waste management plan submitted with any development application
        for a Material Change of Use (MCU):
        (a)   any Residential use with more than 15 dwellings or accommodation units;
        (b)   any Business use with a total use area greater than 500m²;
        (c)   all environmentally relevant activities (as defined by Schedule 2 of the Environment Protection Regulation 2008);
        (d)   construction or demolition of a building other than construction of a Dwelling house, or Class 10 building; and
        (e)   any other developments as specified by Council’s Waste Management Officer (identified as part of a preliminary application
              or as an information request).

 (4)    Subject to the scale of the development and the discretion of the Manager Environmental Health, a waste management plan may
        be submitted as a condition of approval for a MCU, and be approved prior to the issue of a development permit – operational
        works.


NOOSA PLAN 2020                                                                                                                   Page 88 of 99
Log in to download the original file

2020-07-16-sm-agenda-item-1-attachment-5-final-noosa-plan-2020-part-8-10-schedules-appendix.pdf · 19.9 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.