Council archive · source document
Volume 2 - Code Responses · 132006.823
COLUMN 1 COLUMN 2 ASSESSMENT
SPECIFIC OUTCOMES PROBABLE SOLUTIONS (if code assessable)
d) a combination of the principles in these Engineering Design Standards Roads, Drainage
documents; and Earthworks and the Queensland Design Code for
AND Residential Streets.
Drainage will be designed in accordance with the
Noosa PSP5 Engineering Design Standards
Roads, Drainage and Earthworks and Queensland
Urban Drainage Design Manual.
S7.2 Complies with specific outcome.
Erosion and sediment control measures are Development proposal complies with the
designed and implemented in accordance with the prescribed solution. Refer to the details outlined
Institution of Engineers Australia (Queensland Division) previously and the Bayview Noosa Hydrology and
Soil Erosion and Sediment Control - Guidelines for Stormwater Management Plan prepared by WBM
Queensland Construction Sites. Oceanics Australia.
Environmental Protection
O8 S8.1 Complies with probable solution.
Roads and stormwater drainage infrastructure are Roads and stormwater drainage follow the edge of Accessways and stormwater drainage follow
located and aligned so as to existing disturbed areas, or alternatively, these existing access tracks across the site wherever
a) minimise disturbance to native vegetation and/or works are co-located within a combined utility possible to minimise disturbance. The overall
other habitat areas; corridor; Viridian site including Stage 3 has been heavily
b) protect and maintain wildlife corridor AND cleared by the previous owner and disturbed by
movements and the safety of native fauna; uncontrolled vehicular access across the site. The
c) minimise changes to the hydrological regime, development of the entire property including Stage
including drainage patterns, run-off and water 3 incorporates significant revegetation of the
quality; property to improve native vegetation and wildlife
d) avoid crossing watercourses, drainage lines and corridors through the site.
wetlands, but where such crossings are S8.2
unavoidable, disturbed areas are reinstated and Roads avoid native vegetation and provide for fauna There are no roads as such. The private accessways
revegetated on completion of works; and underpasses and associated fencing where within the resort are low-speed shared vehicle
e) minimise bulk earthworks. appropriate; pedestrian movement links unlikely to cause
AND problems for fauna.
Volume II: Code Responses
Viridian Noosa Project
Viridian Stage 3
Transport, Roads and Drainage Code 11 April 2006 Page 108
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Volume 2 - Code ResponsesRelated documentApplication case desk ↗