18.0     WATER SUPPLY AND SEWERAGE RETICULATION CODE

18.1     Water supply31

                     COLUMN 1                                                      COLUMN 2                                   ASSESSMENT
               SPECIFIC OUTCOMES                                PROBABLE SOLUTIONS (if code assessable)
Design and construction (water)
O1                                                           S1.1                                             Complies with specific outcome.
Water supply infrastructure                                  Water supply infrastructure is designed in       No new Council infrastructure is proposed as part
a) meets the needs of the users;                             accordance with Section 3 of PSP6 Engineering    of the development. The development requires
b) is designed to be compatible with existing                Design Standards Water and Sewerage and As       connection to the Noosa High Level Zone water
   infrastructure; and                                       Constructed data submitted in accordance with    supply for areas above RL 50m and to the Noosa
c) is designed using materials that are suitable for         Section 7 of PSP6 Engineering Design Standards   Low Level Zone for areas below this level. The
   the use, durable, easy to maintain and cost               Water and Sewerage.                              development represents a small increase in ET
   effective, taking into account the whole of life                                                           over the previously adopted scheme detailed in the
   cycle cost and Council s maintenance inventory.                                                            existing Development Approval. Previously
                                                                                                              approved development was 6 ET in the High Level
                                                                                                              Zone and the proposed scheme is 8 ET. In the
                                                                                                              Low level Zone, the previously approved scheme
                                                                                                              was 116 ET and this scheme represents 130 ET.

                                                                                                              The previous scheme was analysed by Council s
                                                                                                              consultants and was shown to not adversely impact
                                                                                                              on the existing reticulation system. Preliminary
                                                                                                              assessment of the proposed development indicates
                                                                                                              that the levels of service required by Council can
                                                                                                              be achieved with no additional water supply
                                                                                                              reticulation infrastructure being required.
                                                                                                              Council s consultants will be commissioned to
                                                                                                              confirm the suitability of the existing system.


31 Council may require Water Supply Headworks contributions in accordance with PSP17


                                                                                                                                              Volume II: Code Responses

                                                                                                                                              Viridian Noosa Project
                                                                                                                                              Viridian Stage 3

Water Supply and Sewerage Reticulation Code                                                                                                   11 April 2006     Page 137

Used in these records

About this file

File size
5.7 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Volume 2 - Code Responses.pdf · 5.7 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.