PLANNING & ORGANISATION COMMITTEE MEETING AGENDA 17 JUNE 2014
Co-ordination of Operational Works Assessment
5. Additional application fees apply to Operational Work applications where the different
aspects of the works are lodged separately. Significant savings in application fees
will result if all works are lodged in a single application.
Preparation of a Preliminary Construction Management Plan
6. A preliminary Construction Management Plan must be submitted with the Operational
Works application and must address the following:
(a) traffic management during all aspects of the construction phase including:
(i) a Traffic Management Control Plan in accordance with the Manual of
Uniform Traffic Control Devices (MUTCD) detailing all temporary signage
and traffic control measures prior to construction
(ii) maintenance of safe pedestrian access for the areas affected by the
works during and after daily construction has ceased
(iii) proposed fencing to the site during the construction phase of the
development
(iv) provision for worker car parking
(b) maintenance and protection of water quality and existing drainage lines through
the construction site, through the implementation of appropriate erosion and
sediment control measures
(c) works programme identifying key components of the works and their respective
durations
(d) establishment of a communication protocol with the general public, adjoining
owners, emergency services and local businesses to advise of agreed
construction times, impacts on traffic, services and other relevant issues
(e) identification of complaint management procedures including:
(i) contact details for the on-site manager
(ii) dispute resolution procedures
(f) it is acknowledged that the preliminary Construction Management Plan will be a
draft document requiring finalisation upon appointment of the Principal
Contractor employed to construct the works and a final document will be
required to be submitted at the Pre-Start Meeting for the project.
Unitywater
7. Connection to Unitywater live water mains and the Unitywater live sewer system must
be undertaken by Unitywater at the applicant’s cost.
8. A 150mm diameter watermain is located within the road boundary fronting the
development site in David Low Way. Construction works, heavy traffic crossing the
main, excessive vibration and excavation close to the main may cause damage to the
pipe. Extreme care is required when working close to this infrastructure. All costs
associated with repair, replacement or alteration of infrastructure must be met by the
applicant.
B. Find the following are sufficient grounds to justify the decision despite the conflict with the
Planning Scheme:
1. The proposed small low cost permanent and visitor accommodation provides housing
diversity ideally located in close proximity to the Peregian Beach neighbourhood
centre and other social infrastructure.
Page 12 of 112
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.