PLANNING & ORGANISATION COMMITTEE MEETING AGENDA 17 JUNE 2014
Car Parking
20. A minimum of 12 car parking spaces must be provided and marked on the site. The
works must be undertaken in accordance with an Operational Works approval and
must include in particular:
(a) 3 visitor parking spaces within the total, which are clearly marked for that
purpose and accessible at all times for visitor use
(b) crossfalls and gradients in accordance with Australian Standard AS/NZS
2890.1:2004 - Parking Facilities
(c) garages, including door openings, in accordance with section 5.4 of Australian
Standard AS/NZS 2890.1:2004 - Parking Facilities
Pedestrian
21. Pedestrian facilities must be provided for the development. The works must be
undertaken in accordance with an Operational Works approval and must include in
particular a 2 metre wide concrete footpath within the road verge for the entire length
of the site’s frontage to David Low Way.
Stormwater Drainage
22. The site must be provided with a stormwater drainage system connecting to a lawful
point of discharge. The works must be:
(a) generally in accordance with drawing number 17011-SW1 B prepared by SCG
Consulting Engineers
(b) undertaken in accordance with an Operational Works approval.
Electricity and Telecommunication Services
23. Unless otherwise stipulated by telecommunications legislation at the time of
construction, the development must be provided with all necessary conduits, pits and
pipes to accommodate the future connection of optic fibre technology
telecommunications.
24. Certification must be submitted to Council from all relevant service providers which
certifies that the development has met the requirements of this Decision Notice and
all applicable legislation at the time of construction.
Earthworks and Retaining Walls
25. All fill and associated batters must be undertaken in accordance with an Operational
Works approval, and contained entirely within the subject site unless written
permission from the respective landowner(s) is provided to Council.
Damage to Services and Assets
26. Any damage caused to existing services and assets as a result of the development
works must be repaired at no cost to the asset owner at the following times:
(a) where the damage would cause a hazard to pedestrian or vehicle safety,
immediately; or
(b) where otherwise, upon completion of the works associated with the
development.
Any repair work which proposes to alter the alignment or level of existing services
and assets must first be referred to the relevant service authority for approval.
Page 9 of 112
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.