PLANNING & ORGANISATION COMMITTEE MEETING AGENDA 17 JUNE 2014
ENVIRONMENT
Waste Storage
27. The developer must provide waste storage and disposal facilities in accordance with
Planning Scheme Policy 9, Waste Management, including an external imperviously
paved area correctly sized for all refuse and recycling containers and suitably
screened from public places and neighboring properties.
28. A bin wash area is required with a cold-water tap, hose and drain outlet connected to
sewer, via a bucket trap. The drain outlet must be designed to prevent storm water
entry to the sewerage system which can be achieved by a bunded area, with a nib
wall height of 100mm maximum, enclosing a wash area of 700mm x 700mm
minimum (max 0.7m²). Alternatively the waste area can be roofed, or any other
appropriate design approved by council that would prevent storm water entry to the
sewer.
Noise
29. Written certification is required from a suitably qualified person confirming that sound
pressure levels from all mechanical plant and equipment comply with the following :
(a) Air-conditioning and Refrigeration
7am to 10pm: Maximum level allowable = background + 5dB(A)
10pm to 7am: Maximum level allowable = background + 3dB(A)
(b) Pumps
7am to 7pm: Maximum level allowable = background + 5dB(A)
7pm to 10pm: Maximum level allowable = background + 3dB(A)
10pm to 7am: No audible noise.
Assessment and certification is required immediately after installation of the
equipment and prior to any occupation of the building. All equipment should be
operating at the same time to test the overall noise level created, with the
measurement location at either the residential boundary or outside the most exposed
part of an affected building - whichever is the closest to the plant/equipment.
30. The certification must be submitted to Council, which certifies that operational noise
from any fixed plant and equipment complies with the requirements of this Decision
Notice.
UNITYWATER
31. Reticulated water supply and sewerage must be provided to the development.
32. Construction activities must not impede the access of Unitywater or Fire Brigade
personnel to vital infrastructure (eg. valves, fire hydrants and sewer access
chambers).
33. The fire-fighting demand on Unitywater’s water supply system from the development
must not exceed 15 litres per second.
34. The existing 150mm diameter asbestos concrete watermain in David Low Way must
be replaced for the full frontage of the development site with DICL pipes. The
replacement works must be completed prior to placing construction materials/site
offices over or adjacent to the water main alignment.
Page 10 of 112
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.