Original source · versioned page text
Attachment D- Construction Management Plan
Plans and drawings
This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).
Log in to see the plans as drawn ABN 51 640 311 842
OFFICES
Sunshine Coast | Brisbane | Gold Coast
Introduction
This Construction Management Plan (CMP) has been developed to describe how the project
management team shall implement and conduct its allocated site management responsibilities
during the construction phase of the residential dwelling at 20 Park Crescent, Sunshine Beach. The
fundamental aim of this plan is to ensure all construction is properly facilitated, integrated, and
coordinated to deliver certainty to the objectives of the project.
This CMP is intended to outline general site specific construction risks, and should be used in
conjunction with the builders methodology and site specific requirements to manage safety and the
environment.
CMP Scope
This plan provides a holistic approach that:
advises how the project management team will comply with the requirements of the
construction for the site;
defines the project objectives and targets of particular relevance to the construction phase;
describes constraints specific to the construction phase and the project in general; and
describes the process for the identification and control of risks specific to the construction
phase;
Site Location & Description
Summary of site location, description, specific features:
Figure 1: Site Location
The site area is 588m2, with levels falling from the property frontage to the rear over approx. 11m.
There are residential properties on either side and vegetated coastline to the rear.
Proposed Works
The proposed works require the construction of a 3-storey residential house and a sloping site
outlooking Sunshine Beach. The preliminary Concept Drawings provided by Teeland Architects (Project
2001), outline that there is to be a below ground room and 2 floors above ground. Construction
materials appear to be industry standard and a mix between a concrete structure and timber finishing.
Page 3 of 9
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.