There is no major road or services upgrades external to the site, and the works appear to be contained
to normal residential building works. Demolition of the existing house and some vegetation will be
required prior to construction of the new house.
        Precedence
Where ambiguity is detected between local and state government processes and requirements in
this CMP and the former will take precedence.
        Interface with other project plans and processes
The construction management plan forms part of an integrated set of management plans and should
be read in conjunction with these other plans.

        Construction Management
        Approach
The major external constraints on the project are:
        Access to site (only available from the street frontage);
        Residnetial buildings on either side of the site;
        Steep sloping site;
        Undertaking works with minimal impact on neighbours;
Upon commencement, the project team's immediate tasks will be to:
        Locate site specific facilities for all workers;
        Undertake a survey of the site and complete a dilapidation report of surrounding properties
         (if required) and assets;
        Confirm the locations of existing services and obtain all necessary permits and licences and
         approvals;
        Arrange for the installation of temporary services – power, water and sewer to service the
         site works and the amenities.
        Approvals
Development approval is required for the works covering the excavation, basement and construction
works. We foresee that the development approval will contain conditions that certain reports will
need to be completed, submitted and approved before works can commence. Some of these reports
needing approval will most likely be:
        Construction Management Plan
        Erosion and Sediment Control
        Geotechnical Slope Stability Assessment
Prior to commencing temporary modification of traffic arrangements, further approvals will be
required from Council including but not limited to:
        Building Design Approval
        Landscape Operational Works
All approvals will be required prior to construction commencing on the site.




                                                                                                    Page 4 of 9
Log in to download the original file

Attachment D- Construction Management Plan.pdf · 670 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.