Attachment D- Construction Management Plan
Plans and drawings
This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).
Log in to see the plans as drawn ABN 51 640 311 842
OFFICES
Sunshine Coast | Brisbane | Gold Coast
Site security
The site will be secured using appropriate fences and/or hoardings. All visitors to the site will be
required to report to the site office, and will be appropriately inducted and registered in a site
attendance log book.
Public / Worker safety
All site staff and subcontractors will be required to complete a site-specific induction before
commencing work on site. The induction will cover aspects relating to safety and amenity, including
access, emergency evacuation procedures, location of first aid facilities, location of amenities, site
hours, material handling, noise and dust management and environmental management. Prior to
commencing works on site, all subcontractors will be required to submit a project specific work
health safety and environmental management plan.
Construction Methodology
Demolition and excavation
Demolition and bulk excavation works will be completed prior to building works commencing on the
site.
Traffic Management
TMP's will be submitted to Council for approval prior to implementation. The frontage of the site
currently contains no footpath. Pedestrian access has been and will continue to be, via the verge.
Pedestrian access will not be affected by the works, during or after the works are completed.
Erosion & Sediment Control (ESC)
Protection of existing drainage lines through the construction site will be maintained through
compliance with Preliminary Sediment & Erosion Control Plan and Details (attached separately Civil
Consulting drawings (attached separately). These drawings are preliminary only and will be finalised
with input from the civil contractor and with input from a CPESC.
Program
Upon appointment of the building contractor, a works schedule and program will be provided to
the supervising engineer/client.
Substructure Works
It is envisaged that substructure works will incorporate construction of pad footings for building
columns and footings for structural wall support. Ones the site is setup- building foundations will be
cast, in-ground services installed and concrete walls poured on site as per the Structural design
(when supplied).
In-ground Services
During substructure works in-ground services installation will take place across the site. These works
will be programmed and co-ordinated to provide safe and efficient access for all trades. In-ground
services include stormwater, sanitary drainage, water mains, electrical services.
Structure
The structure will need to be erected via mobile cranes and/or personnel working from elevated
working platforms. Concrete pumping will need to be provided by a boom and poured within stages.
The roofing sheeting will also need to be craned onto the roof and manually split and carried into
Page 5 of 9
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.