Our Ref: 6520
Council Ref: MCU14/0056


4 February, 2015


Noosa Council
PO Box 141
TEWANTIN QLD 4565



Attn Denis Wallace



Via Email: [email protected]


Dear Dennis,


RE: Proposed Mixed Use Development 125 Myall Street, Cooroy- MCU 14/0056- Response to Information
Request


We act on behalf of Creekgold Pty Ltd, the applicant in relation to the above development application matter.

By way of background-

    1.   the Council issued an Information Request on 19 August, 2014;

    2.   in direct response to a number of items raised within that information request, a change to the application
         was lodged with Council on 19 November, 2014 incorporating amended proposal plan (Site Layout Plan
         14004-DA02 Rev E2). Key changes to the plan included a reduction in the scale of the Retail Business Type
         2- Shop from 1144m2 to 250m2, removal of access to Ferrells Rd and inclusion of a Cooroy Township
         Promotion Kiosk (10m2).

    3.   the Council confirmed by letter dated 24 November, 2014 that the IDAS process did not stop (S 354 of SPA)
         for that type of change and the application remained in the Response to Information Request stage as a full
         response had not yet been submitted.

Consequently, in response to Council‘s Information Request, dated 19 August 2014, we now provide the following –

    a)   Revised Proposal Plans prepared by Verve (Attachment A);
    b) Economic impact response prepared by Foresight Partners Pty/Ltd dated December ,2014 (Attachment B);
    c)   Revision to Civil Engineering Report (Engineering Report and Stormwater Management Plan), prepared by
         vT Consulting Engineers and inclusive of response from Seq water (Attachment C);
    d) Stormwater Quantity Management Plan prepared by Storm Water Consulting Pty Ltd ( Attachment D);
    e)   Earthworks Plan prepared by vT Consulting Engineers (Attachment E);

                                                         1
Log in to download the original file

MCU14_0056 Information Response Cover Letter.pdf · 736 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.