SUPERSEDED -Decision Notice - OPW22 0299 [As Published] · OPW22/0299

of 16

Text shows just the words. Original shows the document exactly as it was published.

                      e.      Include a post out to the local residents advising of the proposed development, the
                              expected time frames and the site contact details
                      f.      Include signage in prominent locations on the boundaries of the site advising of the
                              proposed development, the expected time frames and the site contact details.
                      g.      identification of complaint management procedures including:
                              i.       contact details for the on-site manager
                              ii.      dispute resolution procedures
                      h.      details on the location of external fill/dump sites, the haulage route, type of vehicle to
                              be utilised during filling operations and frequency of usage. NB any damage to the
                              existing road system as a result of haulage operations must be fully repaired at the
                              applicant’s expense.
               12.    Any changes to the details associated with the supervising RPEQ or Principal Contractor
                      during construction, must be notified to council in writing within five business days of the
                      change occurring.
               13.    Any conflict between the development and an existing or proposed service must be referred
                      to the relevant service authority for determination prior to commencement of works.
               DURING CONSTRUCTION
                      Engineering
               14.    The developer must meet any costs to repair damage to any Council asset during
                      construction, where damage is a result of the development works. Damage to assets must
                      be repaired immediately where it creates a hazard to the community. In circumstances where
                      the damage does not create a hazard to the community, it must be repaired immediately on
                      completion of the works associated with the development.
               15.    All works must be supervised by a Registered Professional Engineer of Queensland (RPEQ)
                      who is independent of the Developer and Principal Contractor, and they must certify that all
                      works conform to the Operational Works permit. Where municipal works are involved, such
                      confirmation must be submitted for the respective hold points prior to any site inspection by
                      Council Officers.
               16.    All works must be constructed and work procedure undertaken in accordance with:
                      a.      The approved plans/documents and conditions detailed in this Decision Notice
                      b.      The relevant conditions of the higher order Material Change of Use approval viz.
                              MCU22/0299.01 to which this approval relates
                      c.      All relevant Noosa Council Planning Scheme Policies, standard drawings, standard
                              specifications and guidelines
                      d.      The latest version of the Healthy Waterways document “Water Sensitive Urban Design
                              Technical Design Guidelines for South East Queensland” for all water quality devices
                              to be constructed on site
                      Roadworks (External Roadworks & Road Widening Works)
               17.    All pavement widening or construction of new pavement must join neatly to the existing
                      pavement so that there are no irregularities in line or level resulting at or adjacent to the join
                      for the length of the construction. Where necessary the existing pavement must be brought
                      to a satisfactory standard to allow for the above.
               18.    All street surfacing must consist of a minimum depth of 30mm of an approved hot mixed
                      asphaltic concrete, unless other pavement types are approved as feature areas in
                      intersection thresholds, speed control devices, turning areas, indented parking etc.
               19.    The developer must notify Council’s Traffic Engineer for any works involving the removal or
                      modification of existing Council traffic signs and/or parking bays prior to such works
                      commencing.


                                                                                                         Page 5 of 16
Document Set ID: 22382767
Version: 3, Version Date: 24/04/2023

Used in these records

About this file

File size
185 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

SUPERSEDED -Decision Notice - OPW22 0299 [As Published].pdf · 185 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.