Minor Change Existing Approval 51984 3164 01 · 51984.3164.01
ii. 16 meter minimum diameter cul-de-sac bitumen sealed with kerb and
channel.
iii. Grading and paving of unsurfaced areas and associated drainage.
iv. A footpath for that part of the road frontage of the site.
v. A concrete crossover of adequate dimensions to enable ready ingress
and egress to the site.
The cul-de-sac and the above works shall be constructed as part of the development.
c. Detailed design and documentation for the construction of a stormwater drainline to
service the developed portion of the subject site. The drainline shall not be located on
the dune slope within the property, but shall extend from a suitable point on the
development site across the adjacent site on the east to the Noosa Drive road reserve,
wherein it shall be compatible with the forward planning intentions of that part of the
road reserve. From the Noosa Drive road reserve, the drainline shall follow the existing
steep gully which runs across the north-eastern corner of the adjacent development
site and shall then discharge to Noosa Inlet via a suitably designed outlet structure.
Drainage easements shall be required over the abovementioned drainlines where they
traverse private property.
d. Details of works proposed to re-establish the stability of the toe of the sand dune,
particularly in areas where the slope is over steepened.
e. A detailed stormwater drainage design for the building and site which is to be prepared
having regard to the fact that stormwater should not be dieted onto the sand dune at
the rear of the site. The system is to be designed to ensure that surcharge if the
drainage system due to blockages, ect., will not be directed to the rear of the site.
f. Details of stormwater drainage of the natural and excavated surface of the site during
construction. This drainage shall not be directed towards the rear of the site.
g. Details of proposed method of drainage the swimming pool when required, for
maintenance purposes.
h. Details of the proposed controls to be applied to the building works to ensure that
stormwater is not directed towards the dune face and to ensure that construction
vibrations are kept within controls to be detailed by the Applicant’s Consulting
Geotechnical Engineers. Such controls to be sent by the Applicant’s Consulting
Geotechnical Engineers to ensure that the stability of the sand dune will not be
adversely affected.
i. Details of the period of the year during which construction works, particularly
excavation and foundation construction, should take place.
j. Details of proposal for revegetation of areas disturbed during building and drainage
works and details of any proposed improvements to vegetation within the sand dune
at the rear of the site. These details are to be prepared by the Applicant’s Landscape
Architect and approved by the Applicant’s Consulting Geotechnical Engineers.
k. Calculations to verify that the building will be able to withstand loads imposed by
possible future movement of the sand dune to a depth of 4m. below existing surface
levels, or to the depth of a plane sloping at 27 degrees from the toe of the sand dune,
whichever is the greater. In particular, the calculations will need to verify that the
structure is able to withstand lateral loads imposed by these possible future sand
movements.
l. Calculations to verify the adequacy of the design of the foundation system.
Page 4 of 9
Document Set ID: 23480614
Version: 3, Version Date: 30/01/2025
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Minor Change Existing Approval 51984 3164 01.pdfRelated documentApplication case desk ↗
About this file
- File size
- 188 KB (small file)
- File type
No other editions are linked here.