The information request issued to the applicant requested amended plans be provided illustrating
compliance with the scheme provisions. The applicant submits that the proposed setbacks comply
with Performance Outcome PO12 and provides a well-articulated building with visually screened
private courtyards, dense landscaping has no impact on views and is consistent with the character
of street.
It is agreed that the building is well articulated however, the setback as proposed is not supported.
PO12 details the following requirements:
PO12 Buildings and structures are designed and sited to:
a) provide a high level of amenity to users of the subject site and adjoining premises, including
provision of visual and acoustic privacy;
b) not unreasonably obstruct views or cause overlooking of private open space or habitable
areas of adjoining premises;
c) provide adequate distance from adjoining land uses;
d) preserve existing vegetation that will help buffer development;
e) allow for space and landscaping to be provided between buildings including adequate area
at ground level for landscaping with trees, shrubs, outdoor living and utilities;
f) be consistent with the predominant character of the surrounding area; and
g) protect the natural character and avoid adverse impacts on ecologically important
areas such as national parks, waterways and wetlands.
The southern side of Toolar Street is included in the Medium Density Residential zone and is
currently characterised by the following minimum setbacks.
Address Minimum setback Development
21 Werin Street 6.7 metres Carport and wall of dwelling
Corner lot - side boundary
setback
23 Werin Street 2.6 metres Carport and wall of dwelling
Corner lot - side boundary
setback
23 Toolar Street 4.6 metres Roof eave
24 Toolar Street 5.2 metres Dwelling eave
25 Toolar Street 4.7 metres Dwelling (demolished)
26 Toolar Street 5.2 metres Dwelling eave
27 Toolar Street 6.8 metres Dwelling (demolished)
4.8 metres Stairs (demolished)
28 Toolar Street 3.0 metres Dwelling eave
Corner lot - side boundary
setback
29 Toolar Street 7 metres 2nd storey eave
Page 46 of 108
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.