GENERAL COMMITTEE MEETING AGENDA 14 MAY 2018
FINANCE RISKS MITIGATION
Clashes with Telstra services give rise Contractor is aware of Telstra services attached to bridge.
for contractor claiming variation costs. Relocation plans will be designed in the design phase in close
cooperation with service providers.
Contingency amount being insufficient. Risk is mitigated through appointment of experienced
contractor and contract supervision of experienced
Superintendent.
PROGRAM RISKS MITIGATION
There is the potential that the project is Construction during the typically dry season aims to mitigate
delayed due to wet weather. this. Expected wet weather days are included in the tenderers
timeline.
Resource risk. Casa Engineering have nominated a capable team to
undertake construction.
Structure construction takes longer The contractor is well resourced and has the available
than allowed for. recourses to deliver this project successfully in conjunction
with current works on hand. The use of precast materials such
as concrete piles and deck units reduce the risk of
construction delays.
SAFETY RISKS MITIGATION
Height of existing bridge to be Casa Engineering has extensive experience at working at
demolished and construction of new heights and would be appointed as the Principal Contractor
bridge. responsible for all Workplace Health and Safety of the site.
Prior to construction commencing a safety in design report,
work place health and safety and traffic management plans
will be required to be submitted to Council for review.
Regular audits on contractor compliance with these approved
plans will be undertaken by Council and WH&S teams
throughout construction.
Construction using machinery and The contractor is certified to AS 4801 (Occupational Health &
hoisting involved. Safety Management Systems) and the contractor
demonstrated their capability in WH&S very well in its tender
bid. In addition the contractor is very experienced having
successfully completed several similar type bridge projects
within the past 5 years.
Page 15 of 74
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.