GENERAL COMMITTEE MEETING AGENDA 14 MAY 2018
FINANCE RISKS MITIGATION
Contractor claims for variations This has been mitigated through the lump sum procurement
based on changes required for method with further mitigation through post tender clarifications
design. tying the contractor firmly into the agreed scope of works.
Contractor claims for variations due This has been mitigated through post tender clarifications
later possession of site due delayed providing contractor with most actual programme to ty the
relocation of power lines by contractor firmly into the agreed scope of works
Energex and moreover tender
being awarded later than expected
by contractor.
Clashes with underground services This risk is mitigated by thorough investigation in the previous
give rise for contractor claiming design phase. Relocation plans are designed in close cooperation
variation costs. with service providers.
Preferred contractor is aware of the works involved.
Contingency amount being Risk is mitigated through appointment of experienced contractor
insufficient and contract supervision of experienced Superintendent.
PROGRAM RISKS MITIGATION
There is the potential that the Construction during the typically dry season aims to mitigate this.
project is delayed due to wet
weather
Resource risk Ark Construction Group PTY have nominated a capable team
undertaking construction.
Structure construction takes longer The contractor is well resourced and has the available recourses
than allowed for. to deliver this project successfully in conjunction with current
works on hand.
SAFETY RISKS MITIGATION
Proximity of High Voltage Electricity Energex will relocate the nearby power lines underground prior to
cables. contractor start construction. Noting this process has incurred
significant costs over and above original estimates by Energex.
Construction using machinery and The contractor is certified to AS 4801 (Occupational Health &
hoisting involved, possible Safety Management Systems) and demonstrated their capability
occurring of various safety issues. in WH&S very well in its tender bid.
In addition the contractor is very experienced having completed
10 bridge projects within the past 5 years.
ENVIRONMENTAL HARM RISKS MITIGATION
There is risk that the works impact Council has incorporated environmental requirements as part of
on the environment because of the the contract. The contractor must also engage a Spotter Catcher
construction works within the and develop their own Environmental Management plan (EMP) to
Cooroy Creek further minimize risks.
The superintendent and Council staff will closely monitor the
construction phase to ensure impacts are minimised.
SCOPE AND QUALITY RISKS MITIGATION
Risk of not meeting project To be managed through Council staff reviews supported by
objectives specialist consultants.
PUBLIC DISRUPTION AND MITIGATION
COUNCIL REPUTATION RISKS
Traffic disruption due total road During construction a short detour is available via Emerald St and
closure at the site location. Garnet ST / Sportsground Parade.
Pedestrians can walk through the Apex Park and along the
Cooroy sporting complex. The detour will be sufficient marked
using signs.
Council will provide communications to the community leading up
to and during the project.
Noise from plant and equipment This will be minimised where ever possible and where possible
may be a cause of disruption to working during normal working hours.
local residents.
Page 8 of 74
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.