Decision Notice - 010.2006.00002554.001 [As Published] · 132006.2554

of 11

Text shows just the words. Original shows the document exactly as it was published.

NOOSA COUNCIL IDAS Development Application Decision Notice                                                 4 of 11


10.    Buildings and structures (including swimming pools, sheds, tennis courts or outbuildings) are not
       constructed under overhead electricity transmission lines, or within any easements.

11.    Security in the form of a cash bond or trading bank guarantee to the sum of $5 000 must be submitted, to
       secure performance of all conditions of this approval, prior to the issue of a Development Permit for
       building works. The cash bond or trading bank guarantee will be returned on performance of the
       conditions of approval less any costs incurred by Council in respect of enforcing performance of this
       permit.

12.    The Development Permit for a material change of use lapses if the use has not happened by 10 January
       2011, unless an application to extend the currency is approved by Council.

Building Services

13.   The development must be undertaken and operated in a manner that causes no detrimental effect upon
      the amenity of the neighbourhood by reason of the creation of excessive noise, lighting nuisance or other
      emissions.

14.   Fences/walls and combined retaining walls shall not exceed 2.0 metres above natural ground level.

15.   Where a wall of a building or structure is less than 750mm from the side or rear boundary, the wall is to be
      maintenance free.

16.   A condition survey is to be carried out of adjoining buildings, structures and services prior to any
      demolition works or construction works taking place on site. If distress already exists, a photographic
      survey shall be undertaken, the distress measured and a plan to monitor changes to distress shall be
      implemented.

17.   Infrastructure including reticulated water, sewerage, stormwater, and electricity are to be protected from
      damage and made safe to the standard required by the regulatory authority;

18.   All infrastructure must be disconnected, capped or sealed including--
      18.1   electricity meters removed and electrical wires disconnected; and
      18.2    telephone lines are disconnected; and
      18.3   high-speed data cables and television provider boxes are disconnected and removed to the
             standard required by the regulatory authority;

19.   All building materials containing asbestos, including asbestos cement sheeting or roofing and lagging,
      must be removed from the building and disposed of in accordance with industry best practice.

20.   Waste generated during construction must be stockpiled in a centralised location and covered as required
      to prevent material being blown onto adjoining properties including the road reserve or food waste from
      generating vermin. All site waste must be disposed of to an approved waste disposal facility either directly
      or via an approved waste receptacle and collection service. Storage areas are to be located near the
      temporary access to the site so that access can be gained with out damage to infrastructure.

21.   A temporary crossing must be provided to protect road reserve infrastructure including kerb and channel;

22.   Any damage to footpaths, street plantings, kerb and channel or roadways at the removal site, the
      relocation site or between the sites must be repaired or reinstated to at least pre-existing conditions.

23.   Sediment and erosion control measures must be placed on site prior to the works commencing and shall
      be maintained until all works are complete. The erosion and sediment control measures shall be in
      accordance with the “Best practice guidelines for control of stormwater on building sites” prepared by
      Healthy Waterways (copy attached or available at www.healthywaterways.org).

24.   All disturbed areas must be revegetated or otherwise stabilised at the completion of the works. Disturbed
      areas are revegetated using species identified in PSP3 – Landscaping Plants and Guidelines

25.   The transportation of all materials to and from the site must be undertaken in a manner such that no
      particle matter escapes onto a public road. All vehicles carrying out materials either to or from the site
      shall be covered to prevent materials including dust being windblown from the vehicle




A c:\docume~1\dwallace\locals~1\temp\bcl technologies\easypdf 5\@bcl@200430cf\@[email protected]

Used in these records

About this file

File size
225 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Decision Notice - 010.2006.00002554.001 [As Published].pdf · 225 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.